CAPM PRACTICE EXAM
1. The process of establishing clear and achievable objectives, measuring
their achievement, and adjusting performance in accordance with the results
of the measurement is called: - ✔️ ✔️ Management by Objectives
2. During the full life cycle of the project, a plot of the project's expected
expenditures will usually follow a characteristic S curve. This indicates that: -
✔️ ✔T️he bulk of the project budget will be spent in the execution phase
3. In which project lifecycle phase would you expect to have the greatest
influence on overall project cost? - ✔️
✔️ Concept
4. Requirement is - - ✔️
✔️Quantified and documented needs of stakeholders,
customer, and sponsor
5. TQM is - - ✔️
✔T️
otal Quality Management: A common approach to
implementing a quality improvement program
6. Which describes Management Information Systems? - ✔️ ✔S️oftware that
an enterprise uses to support business and administrative operations
7. The type of planning that is equated with more specific data or is detailed
in nature is called: - ✔️
✔️Tactical
8. What are the different types of costs in Microsoft Project? - ✔️
✔️Fixed Cost,
Cost Per Use, Standard Cost, Overtime Cost
, 9. What is the name of PMI's Organization maturity model for project
management? - ✔️ ✔️OPM3
11. A group of related projects that are managed in a coordinated way that
usually includes an element of ongoing activity is called a: - ✔️
✔️Program
12. Project constraint could be on - - ✔️
✔️Cost, resources, schedule
13. What is true about Project Management Office (PMO)? - ✔️
✔️Support
Project Managers by coaching and mentoring
PMO is a project stakeholder
PMO can terminate projects if required to keep business objectives consistent
14. Projects require project management while operations require business
process management or operations management. Projects can intersect with
operations at various points during the product lifecycle. Which of the
following is not a stage to represent this? - ✔️
✔A️ t each Executing phase
15. Enterprise environmental factors refer to both internal and external
environmental factor that surround or influence a project's success. Of the
following, which is NOT an enterprise environmental factor : - ✔️✔H ️istorical
data
16. A person who is involved in or may be affected by the activities or
anyone who has something to gain or lose by the activity of the project is
called a: - ✔️
✔S️takeholder
17. Large projects may be divided into smaller, more manageable
components known as, - ✔️ ✔s️ ubprojects
1. The process of establishing clear and achievable objectives, measuring
their achievement, and adjusting performance in accordance with the results
of the measurement is called: - ✔️ ✔️ Management by Objectives
2. During the full life cycle of the project, a plot of the project's expected
expenditures will usually follow a characteristic S curve. This indicates that: -
✔️ ✔T️he bulk of the project budget will be spent in the execution phase
3. In which project lifecycle phase would you expect to have the greatest
influence on overall project cost? - ✔️
✔️ Concept
4. Requirement is - - ✔️
✔️Quantified and documented needs of stakeholders,
customer, and sponsor
5. TQM is - - ✔️
✔T️
otal Quality Management: A common approach to
implementing a quality improvement program
6. Which describes Management Information Systems? - ✔️ ✔S️oftware that
an enterprise uses to support business and administrative operations
7. The type of planning that is equated with more specific data or is detailed
in nature is called: - ✔️
✔️Tactical
8. What are the different types of costs in Microsoft Project? - ✔️
✔️Fixed Cost,
Cost Per Use, Standard Cost, Overtime Cost
, 9. What is the name of PMI's Organization maturity model for project
management? - ✔️ ✔️OPM3
11. A group of related projects that are managed in a coordinated way that
usually includes an element of ongoing activity is called a: - ✔️
✔️Program
12. Project constraint could be on - - ✔️
✔️Cost, resources, schedule
13. What is true about Project Management Office (PMO)? - ✔️
✔️Support
Project Managers by coaching and mentoring
PMO is a project stakeholder
PMO can terminate projects if required to keep business objectives consistent
14. Projects require project management while operations require business
process management or operations management. Projects can intersect with
operations at various points during the product lifecycle. Which of the
following is not a stage to represent this? - ✔️
✔A️ t each Executing phase
15. Enterprise environmental factors refer to both internal and external
environmental factor that surround or influence a project's success. Of the
following, which is NOT an enterprise environmental factor : - ✔️✔H ️istorical
data
16. A person who is involved in or may be affected by the activities or
anyone who has something to gain or lose by the activity of the project is
called a: - ✔️
✔S️takeholder
17. Large projects may be divided into smaller, more manageable
components known as, - ✔️ ✔s️ ubprojects