Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

Information Technology Project Management 9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13, Complete Newest Version

Beoordeling
-
Verkocht
-
Pagina's
6
Cijfer
A+
Geüpload op
07-09-2024
Geschreven in
2024/2025

Information Technology Project Management 9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13, Complete Newest Version

Instelling
Vak

Voorbeeld van de inhoud

TEST BANK For Information Technology Project Management
9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13,
Complete Newest Version
activity - ANSWER:an element of work normally found on the WBS that has an
expected duration, cost, and resource requirements; also called a task

activity attributes - ANSWER:information about each activity, such as predecessors,
successors, logical relationships, leads and lags, resource requirements, constraints,
imposed dates, and assumptions related to the activity

activity list - ANSWER:a tabulation of activities to be included on a project schedule

activity-on-arrow (AOA) - ANSWER:a network diagramming technique in which
activities are represented by arrows and connected at points called nodes to
illustrate the sequence of activities; also called arrow diagramming method (ADM)

arrow diagramming method (ADM) - ANSWER:a network diagramming technique in
which activities are represented by arrows and connected at points called nodes to
illustrate the sequence of activities; also called activity-on-arrow (AOA)

backward pass - ANSWER:a project network diagramming technique that determines
the late start and late finish dates for each activity

baseline dates - ANSWER:the planned schedule dates for activities in a Tracking
Gantt chart

buffer - ANSWER:additional time to complete a task; a buffer is added to an estimate
to account for various factors

burst - ANSWER:a single node followed by two or more activities on a network
diagram

crashing - ANSWER:a technique for making cost and schedule trade-offs to obtain
the greatest amount of schedule compression for the least incremental cost

critical chain scheduling - ANSWER:a method of scheduling that takes limited
resources into account when creating a project schedule and includes buffers to
protect the project completion date

critical path method (CPM) or critical path analysis - ANSWER:a project network
diagramming technique used to predict total project duration

dependency - ANSWER:the sequencing of project activities or tasks; also called a
relationship

, discretionary dependencies - ANSWER:the sequencing of project activities or tasks
defined by the project team and used with care because they may limit later
scheduling options

dummy activities - ANSWER:activities with no duration and no resources used to
show a logical relationship between two activities in the arrow diagramming method
of project network diagrams

duration - ANSWER:the actual amount of time worked on an activity plus elapsed
time

early finish date - ANSWER:the earliest possible time an activity can finish based on
the project network logic

early start date - ANSWER:the earliest possible time an activity can start based on
the project network logic

effort - ANSWER:the number of workdays or work hours required to complete a task

external dependencies - ANSWER:the sequencing of project activities or tasks that
involve relationships between project and non-project activities

fast tracking - ANSWER:a schedule compression technique in which you do activities
in parallel that you would normally do in sequence

feeding buffers - ANSWER:time added before tasks on the critical chain if they are
preceded by other tasks that are not on the critical path

finish-to-finish dependency - ANSWER:a relationship on a project network diagram in
which the "from" activity must be finished before the "to" activity can be finished

finish-to-start dependency - ANSWER:a relationship on a project network diagram in
which the "from" activity must be finished before the "to" activity can be started

float - ANSWER:the amount of time a project activity may be delayed without
delaying a succeeding activity or the project finish date; also called slack

forward pass - ANSWER:a network diagramming technique that determines the early
start and early finish dates for each activity

free slack (free float) - ANSWER:the amount of time an activity can be delayed
without delaying the early start of any immediately following activities

late finish date - ANSWER:the latest possible time an activity can be completed
without delaying the project finish date

Gekoppeld boek

Geschreven voor

Vak

Documentinformatie

Geüpload op
7 september 2024
Aantal pagina's
6
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$18.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
kushboopatel6867
5.0
(1)

Maak kennis met de verkoper

Seller avatar
kushboopatel6867 Chamberlain College Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
3
Lid sinds
1 jaar
Aantal volgers
0
Documenten
1282
Laatst verkocht
8 maanden geleden
EXCELLENT HOMEWORK HELP AND TUTORING ,

EXCELLENT HOMEWORK HELP AND TUTORING ,ALL KIND OF QUIZ AND EXAMS WITH GUARANTEE OF A EXCELLENT HOMEWORK HELP AND TUTORING ,ALL KIND OF QUIZ AND EXAMS WITH GUARANTEE OF A Am an expert on major courses especially; psychology,Nursing, Human resource Management and Mathemtics Assisting students with quality work is my first priority. I ensure scholarly standards in my documents and that's why i'm one of the BEST GOLD RATED TUTORS in STUVIA. I assure a GOOD GRADE if you will use my work.

Lees meer Lees minder
5.0

1 beoordelingen

5
1
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen