Which of the following is like a receipt that is given to the owner telling him that
everything regarding the financial aspect of the project has been settled ? - ANSWER:
affidavit of payment
Consent of surety is executed by : - ANSWER: the bonding company
Which type of drawing is completed by the manufacturer or a representative of the
manufacturer - ANSWER: Shop
The term for showing how quickly aspects of the project are being completed by
laborers is called - ANSWER: labor productivity
A(n) _____ will show the important information regarding each chemical on the
project site and is required by osha to be available - ANSWER: Material Safety Data
Sheet (MSDS)
Most contracts required the contractor to prepare record drawings or "as-built"
drawings during the project. This process entails recording ___,____&___ - ANSWER:
actual dimensions, location of utilities and changes in drawings
The main purposes of using a subcontractor - ANSWER: specialized labor for
particular construction task , lower cost for subcontract work and reduced risk for
the contractor
A list of all the cost associated within each aspect of the project and how the
progress payments are figured is an - ANSWER: Schedule of Values
A(n) will track progression of where delays are - ANSWER: submittal log
The supplementary conditions to the contract are additional provisions or
modifications to: - ANSWER: The General Conditions of the contract
When there is an issue that involves claims over____, arbitration is used - ANSWER:
1,000,000
A describe action that leads to accomplishing the project which usually includes
completing the project within the scope of time identified in the contract and within
the budget is a(n) - ANSWER: objective
Submittal of ____,_____ and _____ in a complete and timely fashion is essential for
the smooth execution of the construction contract. - ANSWER: product data, shop
drawings and samples