Which of the following personas is least likely to be a user of the PPM
application?
A. Change Manager
B. Development Manager
C. Financial AdviserAnswer - Financial Adviser
An agile phase can be created for a project from the project workbench if the
com.snc.sdlc.agile.2.0 plugin is activated (T/F)Answer - True
Best practices for setting up a program include:
(2 answers)Answer - 1. A project or demand cannot be included in multiple
programs.
2. Risks and issues for projects are not included in the program roll-up
reporting.
(T/F) A project can be directly part of a portfolio and not part of a
program.Answer - True
A project uses the default schedule, which specifies that work hours are M - F
from 08:00 - 17:00 w/ an hour break from 12pm to 13:00. A change request
with a 13-hour duration starts at midnight. When will the project task link start
and end?Answer - The project task link stars at 08:00 and continues through
until noon. It stops at 13:00 for one hour, and continues until 14:00.