COMPLETE 170 QUESTIONS AND CORRECT DETAILED
ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+
A license is required when a person/firm
- installs a boiler
-repairs a boiler
- installs an unfired boiler
- repairs an unfired boiler
- all of the above - ANSWER: All of the above
T/F: License Is issued to a person designated as a license holder, and remains with
that person, regardless of change of an employer - ANSWER: True
A contractor may apply for a re-reinstatement of a license after how many days from
the day the suspension? - ANSWER: 90 days
T/F: All on-site workers are also be required to be a licensed. - ANSWER: False,
installers do not need a license
As a license holder, can you pull a permit and then sub out the installation work? -
ANSWER: No, you cannot sub out boiler installation work.
Permit is required for the installation of a:
- boiler pressure vessel or pressure pipe
- replacement of pressure piping
- water heaters less than 15 psi
- All of the above - ANSWER: All of the above
In emergency repair, permit first authorized by the board inspector, or a special bore
inspector shall be filed within or completed by... - ANSWER: 30 days
When should a license holder submit a permit request for installation of a board
press reversal or piping to the department for approval? - ANSWER: Prior to
installation
T/F: A license holder may place boiler pressure vessel or pressure piping into service
prior to contacting the inspector - ANSWER: False
The law that requires all pressure vessels and boilers to be inspected before
activation - ANSWER: KRS 236
The willful violation of any provision of the law referred to in KRS 236 or KAR 815 is
punishable by... - ANSWER: 30 days in jail and maximum $500/day
NBIC - ANSWER: National Board of Inspections and Code