CAPM REVISION TEST WITH ANSWERS

You are evaluating the dependencies that exist currently within your risk management plan to determine
its accuracy. Which of the following is best described as an action to verify that all risks have been
identified, that plans have been created to handle risks, and that the individuals responsible for
responding to the risks are prepared to take action?

A

Risk reassessment

B

Reserve analysis

C

Workaround

D

Risk audit - Answer✔️
✔️Correct answer: Risk audit



A risk audit is an action to verify that all risks have been identified, that plans have been created to
handle risks, and that the individuals responsible for responding to the risks are prepared to take action.
Basically, a risk audit examines and documents the effectiveness of the risk responses. This is in relation
to dealing with the root causes and identified risks. The risk audit also evaluates the effectiveness of the
risk management process.

A workaround is an unplanne

d response that is created to handle unexpected problems on a project. A risk reassessment is an action
taken to periodically review and adjust the documentation of the risk management plan and risk register.
A reserve analysis is a review of the project's financial resources to compare the current balance against
the projected amount needed.



You are a project manager for a very large company and have taken over a new project that was in the
middle of execution. You would like to see which stakeholders have the greatest influence over your
project. Where is the best place to find this information? - Answer✔️✔️ Correct Answer: Stakeholder
register



It is in the stakeholder register that a project manager would find which stakeholders have been
identified as having the greatest influence over a project. The stakeholder register will also contain
details about particular stakeholders to help understand what knowledge they may have. It also captures
the requirements and various expectations they may have for the project.

,Shanda decided to use an iterative planning technique as a way to work a form of progressive
elaboration on her project. Rolling wave planning is an iterative planning technique that she explored
and decided to utilize. Which of the following is rolling wave planning not applicable to?

A

Work packages

B

Cost analysis

C

Planning packages

D

Release planning - Answer✔️
✔️Correct answer: Cost analysis



Rolling wave planning is an iterative planning technique applicable to work packages, planning packages,
and release planning when using an Agile or waterfall approach. Rolling wave planning involves a
detailed plan of the work to be completed in the near term. The work in the future is planned at a much
higher level.



Rasheed is the lead project manager for a telecommunications organization and is in charge of training
new project managers. One of the new project managers is assisting with managing the communications
process. In evaluating the documents, he notices a document that does not belong in this process.

Which of the following is not an example of a project document that would be an input to the Manage
Communications process?

A

Lessons learned register

B

Resource management plan

C

Stakeholder register

D

Change log - Answer✔️
✔️Correct answer: Resource management plan

,The resource management plan is part of the project management plan, which is an input to the Manage
Communications process. It is not a project document.

The communications management plan includes components of the project, program, or portfolio
management plan that describes how, when, and by whom information about the project will be
administered and disseminated.



Moira begins the event by illustrating the proposed iteration goals alongside reviewing the higher-
priority stories. The development team discusses options for implementation, technical issues,
dependencies, and other requirements. They choose the effort to be performed in the next iteration.
What type of meeting does this best describe?

A

Phase review

B

Status review

C

Backlog planning

D

Iteration planning - Answer✔️
✔️Correct answer: Iteration planning



An iteration planning meeting is used to clarify the details of the backlog items, acceptance criteria, and
work effort required to meet an upcoming iteration commitment. An iteration planning meeting is also
known as a sprint planning meeting. Iterations are timeboxed cycles of development on a product or
deliverable in which all of the work that is required to deliver value is conducted.



You have just implemented a risk response and will need to track its effectiveness. Which process
improves the efficiency of the risk approach throughout the project lifecycle to continuously optimize
risk responses?

A

Control Scope

B

Perform Integrated Change Control

C

Control Quality

, D

Monitor Risks - Answer✔️
✔️Correct answer: Monitor Risks



Monitor Risks is the process of monitoring the implementation of risk response plans, tracking identified
risks, identifying new risks, and evaluating risk process effectiveness throughout the project. The key
benefit of this process is that it allows for project decisions to be based on current information, not
planned information, so risk response can be continually optimized.



It has been a long 6 months of project execution, and you have just completed the last requirement for
the project. Who is responsible for providing formal notice that a contract has been completed?

A

The stakeholders

B

The seller

C

The buyer

D

The project manager - Answer✔️
✔️Correct answer: The buyer



A procurement contract is created between a buyer and a seller, and the seller is the one who is
responsible for doing the work. Therefore, it is the buyer who must determine if the work has met their
expectations.



You have just been reassigned to a new project. As the project manager, which document would you
refer to for information regarding how project requirements will be analyzed?

A

Requirements management plan

B

Scope management plan

C

Requirements traceability matrix

Written for

Course

Document information

Uploaded on
September 24, 2024
Number of pages
38
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$8.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller
Seller avatar
XPERTISEGRADES

Get to know the seller

Seller avatar
XPERTISEGRADES Phoenix College
Follow You need to be logged in order to follow users or courses
Sold
-
Member since
1 year
Number of followers
0
Documents
28
Last sold
-

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions