DBIA EXAM 2 LATEST ACTUAL EXAM
_____ _____ is the belief that there is a technique, method or process that is more
effective at delivering a particular outcome than any other - ANSWER: Best Practice
A Best Practice is the belief that there is a ______ , _____ or _____ that is more
effective at delivering a particular outcome than any other. - ANSWER: - technique
- method
- process
How many best practices are there? - ANSWER: 10
What are the 3 areas that the implementing techniques are categorized into? -
ANSWER: 1. Procurement
2. Contracting
3. Execution
All DB members should be _____ and _____ in the DB process and be knowledgeable
of the differences between DB and other delivery systems. - ANSWER: - educated
- trained
_____ is the essence of Design-Build Done Right - ANSWER: Teaming
What are the 4 key factors enabling Team Alignment? - ANSWER: 1. Early
Involvement
2. Qualifications-Based Selection
3. Cost Transparency
4. Fostering an Environment of Trust
The most successful projects engage core team members in the _____ process,
before advancing beyond _____ design. - ANSWER: - design
- schematic
Early involvement enables deeper participation in _____ practices. - ANSWER:
integrated
Projects should be staffed with individuals that are _____ and ______ in the
implementation of DB best practice and whose _______ are well-suited to the
collaborative nature of the DB process - ANSWER: - educated
- experienced
- personalities
Senior leadership must support DB project _____. - ANSWER: delivery
, _____ should create an organization that supports the successful procurement and
execution of a DB project with key personnel _____ and _____ in DB project delivery
in an _____ and _____ environment. - ANSWER: - Owners
- educated
- trained
- integrated
- collaborative
Executive leadership requires _____ _____. - ANSWER: True Believers
_____ are responsible for an integrated and collaborative environment. - ANSWER:
Owners
Owners are responsible for an _____ and ______ environment. - ANSWER: -
integrated
- collaborative
Owners must sustain an atmosphere of _____ and _____. - ANSWER: - trust
- flexibility
Owners must consistently operate from an _____ DB mindset. - ANSWER: integrated
_____ _____ has a unique definition for each project. - ANSWER: Design Excellence
_____ and _____ should collaboratively and jointly define the design value that best
meet Owner's goals for each project. - ANSWER: - Owners
- Design-Builders
Owners and Design-Builders should collaboratively and jointly define the _____
_____ that best meet Owner's goals for each project. - ANSWER: Design Value
_____ _____ is the time from Notice of Award to the end of the warranty period. -
ANSWER: Post Award
Post Award is the time from _____ __ _____ to the end of the _____ period. -
ANSWER: - Notice of Award
- Warranty
_____ Management typically focuses on building the project. - ANSWER:
Construction
_____-_____ _____ involves managing people through the ENTIRE process. -
ANSWER: Design-Build Leadership
What are the 5 main stages of DB Leadership? - ANSWER: 1. Project team formation
and alignment.
2. Project pursuit and procurement.
_____ _____ is the belief that there is a technique, method or process that is more
effective at delivering a particular outcome than any other - ANSWER: Best Practice
A Best Practice is the belief that there is a ______ , _____ or _____ that is more
effective at delivering a particular outcome than any other. - ANSWER: - technique
- method
- process
How many best practices are there? - ANSWER: 10
What are the 3 areas that the implementing techniques are categorized into? -
ANSWER: 1. Procurement
2. Contracting
3. Execution
All DB members should be _____ and _____ in the DB process and be knowledgeable
of the differences between DB and other delivery systems. - ANSWER: - educated
- trained
_____ is the essence of Design-Build Done Right - ANSWER: Teaming
What are the 4 key factors enabling Team Alignment? - ANSWER: 1. Early
Involvement
2. Qualifications-Based Selection
3. Cost Transparency
4. Fostering an Environment of Trust
The most successful projects engage core team members in the _____ process,
before advancing beyond _____ design. - ANSWER: - design
- schematic
Early involvement enables deeper participation in _____ practices. - ANSWER:
integrated
Projects should be staffed with individuals that are _____ and ______ in the
implementation of DB best practice and whose _______ are well-suited to the
collaborative nature of the DB process - ANSWER: - educated
- experienced
- personalities
Senior leadership must support DB project _____. - ANSWER: delivery
, _____ should create an organization that supports the successful procurement and
execution of a DB project with key personnel _____ and _____ in DB project delivery
in an _____ and _____ environment. - ANSWER: - Owners
- educated
- trained
- integrated
- collaborative
Executive leadership requires _____ _____. - ANSWER: True Believers
_____ are responsible for an integrated and collaborative environment. - ANSWER:
Owners
Owners are responsible for an _____ and ______ environment. - ANSWER: -
integrated
- collaborative
Owners must sustain an atmosphere of _____ and _____. - ANSWER: - trust
- flexibility
Owners must consistently operate from an _____ DB mindset. - ANSWER: integrated
_____ _____ has a unique definition for each project. - ANSWER: Design Excellence
_____ and _____ should collaboratively and jointly define the design value that best
meet Owner's goals for each project. - ANSWER: - Owners
- Design-Builders
Owners and Design-Builders should collaboratively and jointly define the _____
_____ that best meet Owner's goals for each project. - ANSWER: Design Value
_____ _____ is the time from Notice of Award to the end of the warranty period. -
ANSWER: Post Award
Post Award is the time from _____ __ _____ to the end of the _____ period. -
ANSWER: - Notice of Award
- Warranty
_____ Management typically focuses on building the project. - ANSWER:
Construction
_____-_____ _____ involves managing people through the ENTIRE process. -
ANSWER: Design-Build Leadership
What are the 5 main stages of DB Leadership? - ANSWER: 1. Project team formation
and alignment.
2. Project pursuit and procurement.