Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

DBIA EXAM 3

Beoordeling
5.0
(1)
Verkocht
-
Pagina's
10
Cijfer
A+
Geüpload op
25-09-2024
Geschreven in
2024/2025

Exam study book Design-Build: Planning Through Development of Jeffrey L. Beard, Michael C. Loulakis, Edward C. Wundram - ISBN: 9780071499965 (DBIA EXAM 3)

Instelling
Vak

Voorbeeld van de inhoud

DBIA EXAM 3 LATEST ACTUAL EXAM
How team members are organized, establishes when parties engage, determines
roles of parties, and determines sequence of design, procurement, and construction
(db, cmar, dbb) - ANSWER: Project Delivery System

how team members are selected (QBS, best value, low price, sole source) - ANSWER:
Procurement Method

how team members are paid (fp, gmp, cost reimbursement, target price, unit price) -
ANSWER: contracting approach

linear, sequential process, A/E selected on qualifications, GC selected on low price,
design is fully completed without input from GC, A/E acting in owner's interests, with
a historically strong bond, process is well-established and understood - ANSWER:
Design-Bid-Build (DBB)

similar org structure to DBB, construction manager selected by QBS or best value,
contractor provides precon services, negotiated gmp contracting approach, open
book estimating process, potential to fast track project, construction cost
determined before design completed, potential issues over what is reasonably
inferable from gmp design documents - ANSWER: construction manager at risk

The owner contracts with one entity (a person or firm) to provide both design and
construction services, designer and contractor have a direct contractual relationship,
selected by QBS or best value, wide spectrum of contracting approaches and
organizational structures, single point responsibility, owner does not manage
designer, owner exposure to claims is significantly reduced - ANSWER: Design-Build

similar to design build, in industrial and power generation sectors, systems and
performance testing are central to scope, contractor will typically perform
engineering with its in-house staff, owner has need for single point responsibility,
contracts include plant and process performance guarantees, contract items include
performance and schedule liquidated damages and limitations of liability - ANSWER:
engineer procure construct (epc)

owner contracts with multiple trade contractors, attributes are typically similar to
dbb, owner's ability to schedule and coordinate the work - ANSWER: Multiple Prime
Contracting

multi-party agreement - all parties equal, QBS procurement and target pricing
contract approach, private sector use (limited at this time), key: owner's ability to
accept risk - ANSWER: Integrated Project Delivery (IPD)

Instead of government building and maintaining major infrastructure (such as
highway, water treatment plant), build and maintenance is outsourced to a private

, company. Opposed by public sector unions. this is not considered a delivery system
but its underlying approaches are delivery systems and typically use DB. multiple
procurement and contracting approaches - ANSWER: public-private partnership (p3)

intense efforts to establish scope early in the process; drives early team formation to
include key trade subcontractors; can enable big decisions to be made early, affect
project outcomes at lowest cost, establish a need for co-location and collaboration,
and compress time during concurrent design and construction - ANSWER: shift left

typically two-phase best value procurement with lump sum contract; owner defines
project requirements and scope of prescriptive work; use of performance-based
technical requirements with limited prescriptive specifications - ANSWER: traditional
design build

design and price are progressively developed after the design-builder is under
contract; final project cost and schedule commitment is not established as part of
the selection process; two phases: preliminary services and final design and
construction services - ANSWER: progressive design build

describe the end result - ANSWER: criteria documents

prescribes how to achieve the end result - ANSWER: bridging documents

prior to bidding, owner undertakes a process to design the project and all of its
details to 100% complete plans and specs. the owner is therefore responsible for
success or failure of details of the design, and warrants the sufficiency of design to
the contractor. the owner is therefore liable to the contractor for any gaps between
plans and specifications and owner's requirements for project performance -
ANSWER: design bid build paradigm

the owner should define its performance requirements and award the contract on
the basis of preliminary design; this makes the design-builder responsible for
completing the design in accordance with the owner's performance requirements.
that also causes the design-builder to warrant the sufficiency of the design to meet
the owner's criteria and the sufficiency of the design to subcontractors/suppliers
that have no design responsibility - ANSWER: design details responsibility

subdivides project by functional elements, focuses on systems and assemblies, useful
for preliminary information and early design phases, aligns with BIM models and
conceptual estimating - ANSWER: uniformat

subdivides work by results/trades, focuses on building materials, products, and
activities, useful for detailed information during final design and construction
phases, and aligns with detailed estimating - ANSWER: masterformat

a specific business need or behavior as seen by an external user of the system;
describe what functions/operations the end product must perform/accommodate;

Gekoppeld boek

Geschreven voor

Vak

Documentinformatie

Geüpload op
25 september 2024
Aantal pagina's
10
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$18.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Beoordelingen van geverifieerde kopers

Alle reviews worden weergegeven
4 maanden geleden

5.0

1 beoordelingen

5
1
4
0
3
0
2
0
1
0
Betrouwbare reviews op Stuvia

Alle beoordelingen zijn geschreven door echte Stuvia-gebruikers na geverifieerde aankopen.

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
tutorsection1 Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
49
Lid sinds
1 jaar
Aantal volgers
8
Documenten
1079
Laatst verkocht
3 dagen geleden

4.9

459 beoordelingen

5
418
4
31
3
7
2
1
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen