1. What defines a Major Building according to A-1001.1 of the Philadelphia
Administrative Code?
o A. Buildings taller than 5 stories
o B. Buildings with a total area of more than 20,000 square feet
o C. Buildings that are more than 3 stories high, more than 40 feet tall, or cover
10,000 square feet or more
o D. All buildings in the commercial district
Answer: C Explanation: A Major Building is defined as one that is more than 3
stories high, more than 40 feet tall, or covers 10,000 square feet or more.
2. What is the maximum height for a building to be considered for Class B
demolition if it is not designated as a Major Building?
o A. 30 feet
o B. 40 feet
o C. 50 feet
o D. 60 feet
Answer: B Explanation: Buildings not designated as Major Buildings and intended
for Class B demolition should be no more than 40 feet in height.
3. For a building to be classified under Class B demolition, what is the minimum lot
space it must cover?
o A. 5,000 square feet
o B. 7,500 square feet
o C. 10,000 square feet
o D. 12,000 square feet
Answer: C Explanation: The building must cover at least 10,000 square feet of lot
space.
4. Which code outlines the demolition requirements for buildings not classified as
Major Buildings in Philadelphia?
o A. Title 4 of the Philadelphia Building and Occupancy Code
o B. International Building Code (IBC)
o C. Uniform Building Code (UBC)
o D. National Electrical Code (NEC)
Answer: A Explanation: Title 4 of the Philadelphia Building and Occupancy Code
outlines the demolition requirements.
5. What should a demolition plan for a Class B building include?
o A. Details of adjacent property and structures
o B. The exact location of the nearest fire hydrant
o C. Types of materials to be used for the building facade
o D. Plans for installing new electrical systems
Answer: A Explanation: A demolition plan should include details of adjacent
property and structures to ensure safe demolition.
1
,468_PA_PH 468 - Pennsylvania (Philadelphia) Demolition Class B
6. Which of the following is not a requirement for Class B demolition of a building?
o A. The building must be less than 3 stories
o B. The building must be less than 40 feet tall
o C. The building must cover less than 10,000 square feet
o D. The building must be in compliance with the International Building Code
Answer: D Explanation: Compliance with the International Building Code is not
specifically a requirement for Class B demolition, though it is generally important.
7. When demolishing a building, what is the primary concern regarding adjacent
properties?
o A. Ensuring that adjacent properties are not damaged
o B. Ensuring that adjacent properties are evacuated
o C. Installing new utility connections for adjacent properties
o D. Painting adjacent properties for aesthetic purposes
Answer: A Explanation: The primary concern is to ensure that adjacent properties
are not damaged during demolition.
8. What is the required safety equipment for demolition work?
o A. Hard hats, safety goggles, and gloves
o B. Air conditioning units
o C. New office furniture
o D. High-visibility clothing only
Answer: A Explanation: Safety equipment such as hard hats, safety goggles, and
gloves are required for demolition work.
9. Which of the following documents must be obtained before starting demolition
work?
o A. Demolition permit
o B. New construction permit
o C. Landscaping permit
o D. Parking permit
Answer: A Explanation: A demolition permit must be obtained before starting
demolition work.
10. What is the main purpose of the 2018 International Building Code in relation to
demolition?
o A. To provide guidelines for new building construction
o B. To outline safety measures and procedures for demolition
o C. To regulate landscaping practices
o D. To specify requirements for building renovations
Answer: B Explanation: The International Building Code provides guidelines for
safety measures and procedures related to demolition.
11. How should hazardous materials be handled during demolition?
2
,468_PA_PH 468 - Pennsylvania (Philadelphia) Demolition Class B
o A. By leaving them in place until the end of the project
o B. By removing them according to safety regulations
o C. By covering them with temporary tarps
o D. By mixing them with non-hazardous materials
Answer: B Explanation: Hazardous materials should be removed and handled
according to safety regulations.
12. What is the minimum distance a demolition site should be from power lines?
o A. 10 feet
o B. 15 feet
o C. 20 feet
o D. 30 feet
Answer: C Explanation: The minimum distance from power lines should be at least
20 feet.
13. Before beginning demolition, what should be done to ensure utilities are safely
disconnected?
o A. Contact utility companies for disconnection
o B. Turn off utilities at the main switch
o C. Remove utility meters yourself
o D. Cover utility lines with protective materials
Answer: A Explanation: Utility companies should be contacted to ensure safe
disconnection before beginning demolition.
14. Which agency is responsible for enforcing the demolition codes in Philadelphia?
o A. Philadelphia Department of Licenses and Inspections (L&I)
o B. Philadelphia Fire Department
o C. Philadelphia City Council
o D. Pennsylvania Department of Environmental Protection
Answer: A Explanation: The Philadelphia Department of Licenses and Inspections
(L&I) enforces the demolition codes.
15. What type of inspections are required during the demolition process?
o A. Pre-demolition inspection and post-demolition inspection
o B. Random daily inspections
o C. Annual inspections
o D. Inspections only after completion
Answer: A Explanation: Both pre-demolition and post-demolition inspections are
required.
16. What should be done with debris during a demolition project?
o A. It should be sorted and properly disposed of
o B. It should be left on-site until the project is completed
o C. It should be recycled on-site
3
, 468_PA_PH 468 - Pennsylvania (Philadelphia) Demolition Class B
o D. It should be burned safely
Answer: A Explanation: Debris should be sorted and properly disposed of to adhere
to regulations.
17. Which of the following is a key factor in determining the method of demolition?
o A. Type and condition of the building
o B. Color of the building materials
o C. Nearby businesses
o D. Preferences of the demolition crew
Answer: A Explanation: The type and condition of the building are key factors in
determining the demolition method.
18. What should be included in a demolition safety plan?
o A. Procedures for handling emergencies
o B. Details about the building’s history
o C. List of future renovations
o D. Employee dress code
Answer: A Explanation: A demolition safety plan should include procedures for
handling emergencies.
19. How is the term "lot space" defined in the context of demolition?
o A. The total area covered by the building's footprint
o B. The total area of the surrounding neighborhood
o C. The area of adjacent properties
o D. The area of all buildings on the lot
Answer: A Explanation: "Lot space" refers to the total area covered by the building's
footprint.
20. What role does a structural engineer play in a demolition project?
o A. They assess the building's structural integrity and recommend demolition
methods
o B. They design new construction plans
o C. They handle financial planning for the project
o D. They oversee site cleanup
Answer: A Explanation: A structural engineer assesses the building's structural
integrity and recommends appropriate demolition methods.
21. Which regulation governs the handling of asbestos during demolition in
Philadelphia?
o A. Environmental Protection Agency (EPA) regulations
o B. Philadelphia Fire Code
o C. National Building Code
o D. International Energy Conservation Code
4