performance bonds on all public works, what year?
/.Brooks Bill 1972 - Answer-Bill directing A/E's selected on qualifications, what year?
/.Clinger Cohen Act/Defense Procurement Reform Act 1996 - Answer-Allows all federal
agencies to utilize Design-Build. Prior to that no enabling legislation existed allowing
Design-Build.
/.Standard of Care - Answer-The level of quality that any average Design Professional
would be able to perform given the circumstances.
/.Design Bid Build - Answer-Slowest Project Delivery method, linear in nature,
prescriptive (owner knows what they want),
/.Multi Prime - Answer-Project Delivery - Many contracts through Owner
/.CM at Risk - Answer-Project Delivery method allowing the contractor to come on board
very early in design for preconstruction services yet maintains separation between
Designer and Builder contractually.
/.Design Build - Answer-Fastest Project Delivery method, fast tracking possible
overlapping design with construction utilizing incremental packages.
/.Low Bid - Answer-Procurement Method - Most Familiar
/.Negotiated (Qualifications Based) - Answer-Procurement Method - Common for A/E
/.Best Value - Answer-Procurement Method - Qualifications and Price
/.Sole Source - Answer-Procurement Method - Direct
/.Lump Sum - Answer-Contract Format w/ agreed upon fixed price
/.Cost Plus Fee - Answer-Contract Format - contractor reimbursed for actual cost plus
an agreed upon percentage
/.GMP (Guaranteed Maximum Price) - Answer-Contract Format - Combines Cost-Plus &
Lump-Sum, contractor reimbursed for actual cost plus a fee only up to a certain amount.
, /.Unit Price - Answer-Contract Format - cost per piece
/.Target Price - Answer-Contract Format - established cost/benchmark determined
jointly by project team.
/.Trust, Flexibility - Answer-Successful Design Build requires _____ & _______ between
participants
/.Hammurabi - Answer-Singular responsibility for both design & construction was first
codified by ____
/.Bridging Documents - Answer-Owner provided items such as 20% design or more and
provides prescriptive specs at RFP.
/.Spearin Doctrine - Answer-Owner is responsible for implied warranties in the
sufficiency of the specifications.
/.Performance Requirements - Answer-____ ____ should identify end results.
/.Design Build - Answer-Single point of responsibility for both design & construction is
an attribute of what delivery method?
/.Substantiation - Answer-The process of checking milestones along the way for
completeness.
/.Prescriptive - Answer-Owner requiring specific products or methods be instituted by
DB team in order to achieve desired performance.
/.False - Answer-T/F Detailed estimating is the Building systems approach to estimating
/.False - Answer-T/F feasibility estimate is cost model and establishes budget for project
/.True - Answer-T/F key element of quality assurance is keeping communication lines
open between owner and DB
/.True - Answer-T/F in Design/cost relationship of DB, the constructor establishes
design parameters for architect
/.False - Answer-T/F trust is most important thing for DB
/.Schematic estimating - Answer-DB estimating sequence where 15%-20% of design is
completed
/.Trend logs - Answer-Provides baseline budgets and schedules and list estimate trends