Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

DBIA: Principles of Design-Build and Post Award & Contracts Questions With Correct Answers

Beoordeling
-
Verkocht
-
Pagina's
8
Cijfer
A+
Geüpload op
07-10-2024
Geschreven in
2024/2025

DBIA: Principles of Design-Build and Post Award & Contracts Questions With Correct Answers Miller Act 1935 - Answer-Federal Government passed bond requiring payment and performance bonds on all public works, what year? /.Brooks Bill 1972 - Answer-Bill directing A/E's selected on qualifications, what year? /.Clinger Cohen Act/Defense Procurement Reform Act 1996 - Answer-Allows all federal agencies to utilize Design-Build. Prior to that no enabling legislation existed allowing Design-Build. /.Standard of Care - Answer-The level of quality that any average Design Professional would be able to perform given the circumstances. /.Design Bid Build - Answer-Slowest Project Delivery method, linear in nature, prescriptive (owner knows what they want), /.Multi Prime - Answer-Project Delivery - Many contracts through Owner /.CM at Risk - Answer-Project Delivery method allowing the contractor to come on board very early in design for preconstruction services yet maintains separation between Designer and Builder contractually. /.Design Build - Answer-Fastest Project Delivery method, fast tracking possible overlapping design with construction utilizing incremental packages. /.Low Bid - Answer-Procurement Method - Most Familiar /.Negotiated (Qualifications Based) - Answer-Procurement Method - Common for A/E /.Best Value - Answer-Procurement Method - Qualifications and Price /.Sole Source - Answer-Procurement Method - Direct /.Lump Sum - Answer-Contract Format w/ agreed upon fixed price /.Cost Plus Fee - Answer-Contract Format - contractor reimbursed for actual cost plus an agreed upon percentage /.GMP (Guaranteed Maximum Price) - Answer-Contract Format - Combines Cost-Plus & Lump-Sum, contractor reimbursed for actual cost plus a fee only up to a certain amount. /.Unit Price - Answer-Contract Format - cost per piece /.Target Price - Answer-Contract Format - established cost/benchmark determined jointly by project team. /.Trust, Flexibility - Answer-Successful Design Build requires _____ & _______ between participants /.Hammurabi - Answer-Singular responsibility for both design & construction was first codified by ____ /.Bridging Documents - Answer-Owner provided items such as 20% design or more and provides prescriptive specs at RFP. /.Spearin Doctrine - Answer-Owner is responsible for implied warranties in the sufficiency of the specifications. /.Performance Requirements - Answer-____ ____ should identify end results. /.Design Build - Answer-Single point of responsibility for both design & construction is an attribute of what delivery method?

Meer zien Lees minder
Instelling
DBIA: Principles Of Design-Build And Post Award &
Vak
DBIA: Principles of Design-Build and Post Award &

Voorbeeld van de inhoud

Miller Act 1935 - Answer-Federal Government passed bond requiring payment and
performance bonds on all public works, what year?

/.Brooks Bill 1972 - Answer-Bill directing A/E's selected on qualifications, what year?

/.Clinger Cohen Act/Defense Procurement Reform Act 1996 - Answer-Allows all federal
agencies to utilize Design-Build. Prior to that no enabling legislation existed allowing
Design-Build.

/.Standard of Care - Answer-The level of quality that any average Design Professional
would be able to perform given the circumstances.

/.Design Bid Build - Answer-Slowest Project Delivery method, linear in nature,
prescriptive (owner knows what they want),

/.Multi Prime - Answer-Project Delivery - Many contracts through Owner

/.CM at Risk - Answer-Project Delivery method allowing the contractor to come on board
very early in design for preconstruction services yet maintains separation between
Designer and Builder contractually.

/.Design Build - Answer-Fastest Project Delivery method, fast tracking possible
overlapping design with construction utilizing incremental packages.

/.Low Bid - Answer-Procurement Method - Most Familiar

/.Negotiated (Qualifications Based) - Answer-Procurement Method - Common for A/E

/.Best Value - Answer-Procurement Method - Qualifications and Price

/.Sole Source - Answer-Procurement Method - Direct

/.Lump Sum - Answer-Contract Format w/ agreed upon fixed price

/.Cost Plus Fee - Answer-Contract Format - contractor reimbursed for actual cost plus
an agreed upon percentage

/.GMP (Guaranteed Maximum Price) - Answer-Contract Format - Combines Cost-Plus &
Lump-Sum, contractor reimbursed for actual cost plus a fee only up to a certain amount.

, /.Unit Price - Answer-Contract Format - cost per piece

/.Target Price - Answer-Contract Format - established cost/benchmark determined
jointly by project team.

/.Trust, Flexibility - Answer-Successful Design Build requires _____ & _______ between
participants

/.Hammurabi - Answer-Singular responsibility for both design & construction was first
codified by ____

/.Bridging Documents - Answer-Owner provided items such as 20% design or more and
provides prescriptive specs at RFP.

/.Spearin Doctrine - Answer-Owner is responsible for implied warranties in the
sufficiency of the specifications.

/.Performance Requirements - Answer-____ ____ should identify end results.

/.Design Build - Answer-Single point of responsibility for both design & construction is
an attribute of what delivery method?

/.Substantiation - Answer-The process of checking milestones along the way for
completeness.

/.Prescriptive - Answer-Owner requiring specific products or methods be instituted by
DB team in order to achieve desired performance.

/.False - Answer-T/F Detailed estimating is the Building systems approach to estimating

/.False - Answer-T/F feasibility estimate is cost model and establishes budget for project

/.True - Answer-T/F key element of quality assurance is keeping communication lines
open between owner and DB

/.True - Answer-T/F in Design/cost relationship of DB, the constructor establishes
design parameters for architect

/.False - Answer-T/F trust is most important thing for DB

/.Schematic estimating - Answer-DB estimating sequence where 15%-20% of design is
completed

/.Trend logs - Answer-Provides baseline budgets and schedules and list estimate trends

Geschreven voor

Instelling
DBIA: Principles of Design-Build and Post Award &
Vak
DBIA: Principles of Design-Build and Post Award &

Documentinformatie

Geüpload op
7 oktober 2024
Aantal pagina's
8
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$10.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
kartelodoc Harvard University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
145
Lid sinds
1 jaar
Aantal volgers
7
Documenten
8360
Laatst verkocht
4 dagen geleden

Our store offers a wide selection of materials on various subjects and difficulty levels, created by experienced teachers. We specialize on NURSING,WGU,ACLS USMLE,TNCC,PMHNP,ATI and other major courses, Updated Exam, Study Guides and Test banks. If you don't find any document you are looking for in this store contact us and we will fetch it for you in minutes, we love impressing our clients with our quality work and we are very punctual on deadlines. Please go through the sets description appropriately before any purchase and leave a review after purchasing so as to make sure our customers are 100% satisfied. I WISH YOU SUCCESS IN YOUR EDUCATION JOURNEY

Lees meer Lees minder
3.3

25 beoordelingen

5
8
4
2
3
8
2
3
1
4

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen