B: wall-to-wall carpeting
Carpeting is a finish item (like paint or
ceiling tile) that is attached to the
construction and is typically part of the
construction contract. Even though a
sculpture is physically attached to the
construction, it is commissioned directly
with the artist and may be included in the
FF&E budget. Vertical blinds are sometimes
included in the construction contract but
,not as commonly as wall-to- wall carpeting
is. Vending machines can also be part of a
construction contract, but if there is both a
construction and FF&E contract, they are
usually part of FF&E. Although all four of
the items mentioned may be part of either
contract as the client wishes, the question
asks which is generally not.
Which of the following is generally NOT
considered FF&E?
A: vertical blinds
B: wall-to-wall carpeting
C: a commissioned sculpture bolted to a
wall
,D: vending machines built into an opening
C: Base-bid specifications
A base-bid specification calls out a
proprietary material or product but allows
substitutions. An interior designer can use
the term or "approved equal".
In a base-bid specification to ensure that
any substitutions submitted are of equal
quality and gives the chance for the interior
designer to review and approve any
, substitutions prior to being incorporated
into the bid.
In which type of construction specification is
the term “approved equal” most likely to be
used?
A: Performance specifications
B: Descriptive specifications
C: Base-bid specifications
D: Proprietary specifications
QUESTIONS AND CORRECT VERIFIED
ANSWERS|ALREADY GRADED
A+|GUARANTEED TO PASS CONCEPTS
B: wall-to-wall carpeting
Carpeting is a finish item (like paint or
ceiling tile) that is attached to the
construction and is typically part of the
construction contract. Even though a
sculpture is physically attached to the
construction, it is commissioned directly
with the artist and may be included in the
FF&E budget. Vertical blinds are sometimes
included in the construction contract but
,not as commonly as wall-to- wall carpeting
is. Vending machines can also be part of a
construction contract, but if there is both a
construction and FF&E contract, they are
usually part of FF&E. Although all four of
the items mentioned may be part of either
contract as the client wishes, the question
asks which is generally not.
Which of the following is generally NOT
considered FF&E?
A: vertical blinds
B: wall-to-wall carpeting
C: a commissioned sculpture bolted to a
wall
,D: vending machines built into an opening
C: Base-bid specifications
A base-bid specification calls out a
proprietary material or product but allows
substitutions. An interior designer can use
the term or "approved equal".
In a base-bid specification to ensure that
any substitutions submitted are of equal
quality and gives the chance for the interior
designer to review and approve any
, substitutions prior to being incorporated
into the bid.
In which type of construction specification is
the term “approved equal” most likely to be
used?
A: Performance specifications
B: Descriptive specifications
C: Base-bid specifications
D: Proprietary specifications