Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CM 4221 Final Exam Questions and Answer1

Beoordeling
-
Verkocht
-
Pagina's
13
Cijfer
A+
Geüpload op
30-10-2024
Geschreven in
2024/2025

CM 4221 Final Exam Questions and Answer1

Instelling
Vak

Voorbeeld van de inhoud

CM 4221 Final Exam Questions and Answers | Latest
Update | 2024/2025 | Already Passed


Project Lifecycle - ANSWER 1) Establish the Need
2) Engineering & Design
3) Bidding & Award
4) Construction
5) Project Close-out
6) Operation and Maintenance

Project Lifecycle - Engineering and Design - ANSWER - Hire primary design team
- develop project layout
- manage planning and scope

Environmental Impact Statement - ANSWER "EIS" - submitted by the designer only
if needed

Scoping - ANSWER Management Activity: One of the most important
responsibilities of the owner and sets design objectives for A/E

Letter of Intent (LOI) - ANSWER When an owner issues a notice of award to the
winning contractor.

Notice to Proceed - ANSWER Contractor can legally start work when the owner
gives this

Certificate of Occupancy - ANSWER Granted once final inspections are passed

Project Close Out - ANSWER Retainage is paid, wavier on liens once all parties
have been paid, and warranty period begins

Commissioning - ANSWER Done throughout industrial projects but completed at
project close out on commercial projects. Basically a "check" that all appliances and
other materials meet the specs and work properly. Performed by independent agents
(3rd party). Focuses on MEP.

Warranty - ANSWER Contractor warrants certain aspects from failure/repair during
project closeout. Usually a set time period.

O & M Manuals - ANSWER Provided by contractor to owner that outlines the
project and includes info on performing services & repairs to project components.

As-built documentation - ANSWER Records all actual info for future repairs during
project closeout

, Project delivery system - ANSWER The contractual relationships between the
project team members. Determines when project team members are needed and
when they are procured. One of the first key risk management issues.

Delivery Methods - ANSWER Design Bid Build, multi-prime contracting, CM at Risk,
Design build, Integrated Project Delivery.

Management Methods - ANSWER Agency Construction Management & Program
Management

Procurement Methods - ANSWER Low-Bid, Best Value, Qualifications Based

Design Bid Build - ANSWER Owner has separate contracts with prime architect
and general contractor. Construction costs known prior to starting work, works well
with conventional construction projects, contractor absorbs most construction risks.
Lack of construction input during design, competitive atmosphere creates adversarial
relationships, lowest bid award creates marginal subcontractors, and unethical
bidding practices.

Multi-Prime Contracting - ANSWER Owner has separate contracts with MULTIPLE
contractors AND a prime architect. More control of project by the owner (acts as
GC), ease in phasing the project and potential cost savings. Multiple contracts create
many phases to manage, gradual determination of final cost, tension over project
leadership, additional owner resources needed and safety can suffer.

CM at Risk Method - ANSWER Owner has separate contracts with construction
manager/general contractor and architect/engineer. Construction input during
design, useful for complex and high risk projects (innovation), reduction is
constructibility risks and the owner has more design control. Difficulty in negotiating
GMP, project costs not known until late in engineering and design phase, no contract
between construction firm and designer and additional fees required for construction
firm during design.

Design Build Method - ANSWER Owner has one contract with design/builder firm.
Construction input during design, useful on large and complex projects, allows for
innovation and completes projects faster (fast-track projects). Lack of input by the
owner in design and construction, reduced owner control, total project cost may be
unknown until construction phase, less competition during bidding and potential to be
difficult to estimate.

Design Build firm - ANSWER one company, joint venture, contractor led or designer
led

Design Build Operate Maintain (DBOM) - ANSWER Design builder provides O&M
services for a set period of time.

Build Operate Transfer (BOT) - ANSWER Design Build Finance Operate Maintain
and commonly called Public-Private Partnerships

Geschreven voor

Vak

Documentinformatie

Geüpload op
30 oktober 2024
Aantal pagina's
13
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$18.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
tutorsection1 Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
49
Lid sinds
1 jaar
Aantal volgers
8
Documenten
1079
Laatst verkocht
1 week geleden

4.9

459 beoordelingen

5
418
4
31
3
7
2
1
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen