UPDATED 2024/2025
Holding a public hearing
- CORRECT ANSWER Which of the following is not one of the typical six steps
involved in permit process Construction documents
- CORRECT ANSWER Plans and specifications necessary for obtaining a permit are
known as _____
Finished floor level
- CORRECT ANSWER The architectural abbreviation "FFL" signifies _____
Heating ventilation and air conditioning
- CORRECT ANSWER HVAC stands for Plan
- CORRECT ANSWER A(n) _____ view of a construction drawing shows the proposed
construction as if it were being viewed from the air.
Transverse section
- CORRECT ANSWER A cross section view of a building is also known as a
_____Detail
- CORRECT ANSWER A drawing showing a particular building element on a larger
scale is known as a ____
What number the detail is and on what page it appears
- CORRECT ANSWER A reference symbol indicates _____
Add or subtract the existing dimensions to determine the missing dimension -
CORRECT ANSWER If a dimension is missing from the floor plans, the plans examiner
should first___
height of foundation walls
- CORRECT ANSWER Which of the following is not typically shown on a foundation
plan?
Finished roof elevation
- CORRECT ANSWER A site plan does not typically show _____
Trusses or rafters
- CORRECT ANSWER A roof plan does not typically show
Engineering details
- CORRECT ANSWER Structural calculations or soils reports are examples of
Site
, - CORRECT ANSWER A parcel of land bounded by a lot line or a designated portion of
a public right-of-way is known as a _____
Construction type
- CORRECT ANSWER Which of the following is not typically one of the first 3 items to
check in a zoning review?
check the construction documents for compliance with the code
- CORRECT ANSWER The primary purpose of conducting a building plan review is to
Special inspections
- CORRECT ANSWER Which is not considered one of the 3 types of inspections
performed by building departments
Top of foundation clearance above grade
- CORRECT ANSWER All are verified during a footing inspection except
Concrete slab-on-grade
- CORRECT ANSWER During the _____ inspection, the inspector checks base fill
material type and thickness and vapor barrier placement
fire-blocking or draft-stopping
- CORRECT ANSWER At the framing inspection, all concealed spaces are checked to
determine if _____ is required
Carpeting
- CORRECT ANSWER All of the following must be present at the final inspection except
______
What must be done to correct any violations noted during inspection
- CORRECT ANSWER A field correction notice informs the contractor of _____
Notice of violation
- CORRECT ANSWER When compliance can't be obtained through a field correction
notice alone, a _____ is typically issued
The minimum and maximum penalties are established
- CORRECT ANSWER Which is not typically part of the administrative procedure for
handling a citizen complaint inspection?
Accessibility
- CORRECT ANSWER Which is not specifically listed in the international building code
for the establishment of minimum standards to safeguard the public health, safety and
welfare
International Fuel Gas Code