What is a "Force Account?"
Cost-Plus
Guaranteed Maximum
Unit-Price
A type of allowance for the owner to pay for certain items of work
Lump-Sum
None of the above
Definition 2 of 66
Bid drawings usually provide very little detail about the specific requirements of site work
operations. The drawings will give details of the new construction required for the project but
information about the size and shape of excavations and details of current site conditions are
seldom provided
What is meant by a team approach to estimating, and how can it help an estimator in his or
her work?
Why is the process of measuring excavation different from measuring the work of other
trades?
Why does the estimating process need to be scheduled?
What is the purpose of Cost Estimating?
,Term 3 of 66
What division in RS Means is Concrete?
1
2
3
4
5
None of the above
Term 4 of 66
What is the purpose of Cost Estimating?
1.Programming phase
2.Schematic design
3.Design development
4.Construction documents
• Design-Bid-Build
• Construction Management
• Design-Build
• Determine the Feasibility of Projects
• Calculate an approximate Price of a Project
• Prepare a Value Analysis
• Set the Sales Prices
• Calculate a Bid Price
• Determine Project Budgets for Cost Control
a feasible project can be defined as one where the anticipated value of all benefits exceeds
the estimated total cost of putting the project in place
,Term 5 of 66
Which one of the following defines cost estimating?
a) An evaluation of a future cost
b) An accurate forecast of future cost
c) An attempt to determine the likely cost of some building work before the work is
done
d) A process of analyzing a specific scope of work and predicting the cost of
performing the work.
e) b and c above
f) All of the above
Term 6 of 66
What is meant by a team approach to estimating, and how can it help an estimator in his or her
work?
• An evaluation of a future cost
• An attempt to determine the likely cost of some building work before the work is
done
The process of analyzing a specific scope of work
and predicting the cost of performing the work.
The team approach involves the input of managers and experienced field personnel in the
preparation of an estimate rather than having estimators work alone on the task
The cost of hand excavation is generally far high than the cost of other excavation methods.
, Term 7 of 66
Reviews are needed for
a. Equipment
b. Units
c. Unit prices & productivity rates
d. Materials
e. c and d above
f. None of the above
Term 8 of 66
What are the 5 type of takeoffs in Timberline
b) Assembly takeoff
1. Quick Takeoff
2. Item Takeoff
3. Assembly Takeoff
4. Model Takeoff
5. One-time Item Takeoff
he value of the development and the cost of the development
a) Length, Width and Depth or Height
66 Multiple choice questions
Term 1 of 66
What is a "Force Account?"
Cost-Plus
Guaranteed Maximum
Unit-Price
A type of allowance for the owner to pay for certain items of work
Lump-Sum
None of the above
Definition 2 of 66
Bid drawings usually provide very little detail about the specific requirements of site work
operations. The drawings will give details of the new construction required for the project but
information about the size and shape of excavations and details of current site conditions are
seldom provided
What is meant by a team approach to estimating, and how can it help an estimator in his or
her work?
Why is the process of measuring excavation different from measuring the work of other
trades?
Why does the estimating process need to be scheduled?
What is the purpose of Cost Estimating?
,Term 3 of 66
What division in RS Means is Concrete?
1
2
3
4
5
None of the above
Term 4 of 66
What is the purpose of Cost Estimating?
1.Programming phase
2.Schematic design
3.Design development
4.Construction documents
• Design-Bid-Build
• Construction Management
• Design-Build
• Determine the Feasibility of Projects
• Calculate an approximate Price of a Project
• Prepare a Value Analysis
• Set the Sales Prices
• Calculate a Bid Price
• Determine Project Budgets for Cost Control
a feasible project can be defined as one where the anticipated value of all benefits exceeds
the estimated total cost of putting the project in place
,Term 5 of 66
Which one of the following defines cost estimating?
a) An evaluation of a future cost
b) An accurate forecast of future cost
c) An attempt to determine the likely cost of some building work before the work is
done
d) A process of analyzing a specific scope of work and predicting the cost of
performing the work.
e) b and c above
f) All of the above
Term 6 of 66
What is meant by a team approach to estimating, and how can it help an estimator in his or her
work?
• An evaluation of a future cost
• An attempt to determine the likely cost of some building work before the work is
done
The process of analyzing a specific scope of work
and predicting the cost of performing the work.
The team approach involves the input of managers and experienced field personnel in the
preparation of an estimate rather than having estimators work alone on the task
The cost of hand excavation is generally far high than the cost of other excavation methods.
, Term 7 of 66
Reviews are needed for
a. Equipment
b. Units
c. Unit prices & productivity rates
d. Materials
e. c and d above
f. None of the above
Term 8 of 66
What are the 5 type of takeoffs in Timberline
b) Assembly takeoff
1. Quick Takeoff
2. Item Takeoff
3. Assembly Takeoff
4. Model Takeoff
5. One-time Item Takeoff
he value of the development and the cost of the development
a) Length, Width and Depth or Height