Construction Cost Estimating-Najafi |66 Questions| With Complete Answers!!

Instelling
....
Vak
....

Voorbeeld van de inhoud

Name: Score:


66 Multiple choice questions

Term 1 of 66
What is a "Force Account?"

Cost-Plus

Guaranteed Maximum

Unit-Price

A type of allowance for the owner to pay for certain items of work

Lump-Sum

None of the above

Definition 2 of 66
Bid drawings usually provide very little detail about the specific requirements of site work
operations. The drawings will give details of the new construction required for the project but
information about the size and shape of excavations and details of current site conditions are
seldom provided

What is meant by a team approach to estimating, and how can it help an estimator in his or
her work?


Why is the process of measuring excavation different from measuring the work of other
trades?


Why does the estimating process need to be scheduled?

What is the purpose of Cost Estimating?

,Term 3 of 66
What division in RS Means is Concrete?

1

2


3


4

5


None of the above

Term 4 of 66
What is the purpose of Cost Estimating?

1.Programming phase
2.Schematic design
3.Design development
4.Construction documents

• Design-Bid-Build
• Construction Management
• Design-Build

• Determine the Feasibility of Projects
• Calculate an approximate Price of a Project
• Prepare a Value Analysis
• Set the Sales Prices
• Calculate a Bid Price
• Determine Project Budgets for Cost Control

a feasible project can be defined as one where the anticipated value of all benefits exceeds
the estimated total cost of putting the project in place

,Term 5 of 66
Which one of the following defines cost estimating?

a) An evaluation of a future cost

b) An accurate forecast of future cost

c) An attempt to determine the likely cost of some building work before the work is
done

d) A process of analyzing a specific scope of work and predicting the cost of
performing the work.

e) b and c above


f) All of the above

Term 6 of 66
What is meant by a team approach to estimating, and how can it help an estimator in his or her
work?

• An evaluation of a future cost
• An attempt to determine the likely cost of some building work before the work is
done


The process of analyzing a specific scope of work
and predicting the cost of performing the work.

The team approach involves the input of managers and experienced field personnel in the
preparation of an estimate rather than having estimators work alone on the task


The cost of hand excavation is generally far high than the cost of other excavation methods.

, Term 7 of 66
Reviews are needed for

a. Equipment

b. Units

c. Unit prices & productivity rates


d. Materials

e. c and d above

f. None of the above

Term 8 of 66
What are the 5 type of takeoffs in Timberline

b) Assembly takeoff

1. Quick Takeoff
2. Item Takeoff
3. Assembly Takeoff
4. Model Takeoff
5. One-time Item Takeoff

he value of the development and the cost of the development

a) Length, Width and Depth or Height

Geschreven voor

Instelling
....
Vak
....

Documentinformatie

Geüpload op
4 november 2024
Aantal pagina's
31
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$8.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
amzingnurse study smarts
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1562
Lid sinds
2 jaar
Aantal volgers
63
Documenten
3633
Laatst verkocht
4 dagen geleden

4.8

1569 beoordelingen

5
1346
4
184
3
14
2
6
1
19

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen