Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

Asphalt Paving Gc Exam Questions With Solutions

Beoordeling
-
Verkocht
-
Pagina's
14
Cijfer
A+
Geüpload op
05-11-2024
Geschreven in
2024/2025

Asphalt Paving Gc Exam Questions With Solutions

Instelling
FDOT ASPHALT PAVING LEVEL 2
Vak
FDOT ASPHALT PAVING LEVEL 2

Voorbeeld van de inhoud

Asphalt Paving Gc Exam Questions
With Solutions
Base Course - ANSWER- Layer or layers of specified material of designated thickness
or rate of application based on a subbase or subgrade to support the subsequent layers

Bridge - ANSWER- Over a depression; longer than 20'

The subgrade is the top _______ of roadbed upon which the pavement structure and
shoulders are constructed - ANSWER- 18"

Do not use glass in the top _____ of the embankment - ANSWER- 18"

Clear and grub minimum of ____ from each edge of proposed pavement along both
lanes and legs of interchange - ANSWER- 30'

Where clearing and grubbing within the roadway is indicated at a bridge site, clear by
cutting all trees, stumps, etc. to within ______ of the ground or to low water in the full
width of the ROW for a distance of 75' beyond the beginning and end of the proposed
bridge - ANSWER- 8"

Compact the subgrade between the lines ____ inches outside the area occupied by the
pavement structure, including C&G & SW to not less than 95% of max density -
ANSWER- 18"

Pulverize base course material so that the completion of the moist mixing 100% (by dry
weight) passes the 1.5" sieve and a minimum of _____ passes the #4 sieve, exclusive
of gravel and stone retained on the sieve - ANSWER- 80%

#4 sieve - ANSWER- 4.75 mm

Ensure finished surface of base varies neither than 3/8" from a straight edge 10' long
when applied parallel to the CL of the rd, no more than ______ inch from the typical
cross-section on the plans - ANSWER- 1/2"

Thickness of completed modified base is measured at staggered intervals not to exceed
_____ feet in length for two-lane roads - ANSWER- 250'

Use _______ in all base courses as an anti-stripping additive - ANSWER- hydrated lime

Where plans required uniform thickness of base course and the contract provides for
pavement on sq yd bases, thickness of base course is determined from measurements

Page | 1

, taken of the completed base course at intervals not exceeding _____ feet for two-lane
roads - ANSWER- 500'

For HMA, use aggregates with a combined specific gravity of _____ or less - ANSWER-
2.90

ON HMA use pneumo-rollers that are self propelled and have an effective rolling width
of not less than _______ - ANSWER- 60"

Ensure intermediate rolling of HMA is completed before mat temp drops below _____ -
ANSWER- 175 degrees

First step in applying asphalt surface treatment (single) - ANSWER- Clean surface

Last step in applying asphalt surface treatment (single) - ANSWER- Remove excess
aggregate

Spread aggregate for HMA within _____ feet of the application of the emulsion -
ANSWER- 200'

Place asphalt surface treatment (double) within ____ days of the base course being
primed - ANSWER- 7

When rolling aggregate applications for asphalt surface treatment (double) on each trip
of the roller, overlap prior by _____ the width of the roller - ANSWER- 1/2

On portland cement pavement, position lower surface of preformed joint filler on or
below surface of base while upper surface is _____ inches below surface of the slab -
ANSWER- 1/2"

When using surface vibrators on portland concrete, ensure frequency is not less than
______ impulses per minute - ANSWER- 3500

Construct subbase and base beneath concrete pavement to include area _____ inches
in width extending beyond edges to provide stability for paver tracks - ANSWER- 18"

Min. width of any reinforced concrete slab is ______ feet - ANSWER- 16'

Max. length of any reinforced concrete slab is ______ feet - ANSWER- 20'

Exclude all vehicle traffic from newly constructed concrete pavement for a period of not
less than ______ days - ANSWER- 14

Finish joints should not deviate more than ____ inch in the horizontal alignment from a
straight line - ANSWER- 1/4"


Page | 2

Geschreven voor

Instelling
FDOT ASPHALT PAVING LEVEL 2
Vak
FDOT ASPHALT PAVING LEVEL 2

Documentinformatie

Geüpload op
5 november 2024
Aantal pagina's
14
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$11.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Divinehub Exam
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
281
Lid sinds
3 jaar
Aantal volgers
172
Documenten
4254
Laatst verkocht
1 maand geleden
NURSING EXAMS AND STUDY GUIDES

Welcome to the best educational world with the brightest, most amazing, and all complete study materials. I wish you great,easy learning and success throughout your course. Kindly message me if you can\'t find your tutorials

3.9

46 beoordelingen

5
24
4
6
3
9
2
0
1
7

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen