Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

OSCM 373- Exam 2 WITH Q & A

Beoordeling
-
Verkocht
-
Pagina's
16
Cijfer
A+
Geüpload op
08-11-2024
Geschreven in
2024/2025

OSCM 373- Exam 2 WITH Q & A What is the average Wait-Time? - CORRECT ANSWER 30 minutes Working (uses Little Law's rule): Wq = Lq / λ = 4/8 = 1/2 hour = 30 minutes What effect an increase of Server-Utilization has on expected Wait-Time? - CORRECT ANSWER Expected wait time would increase Using the Shortest Processing Time sequencing rule and assuming start time is 0, when is Job C expected to end? - CORRECT ANSWER 8 (cumulative duration/processing time to Job C) What should be your goal when using John's Rule? - CORRECT ANSWER Minimize the time it takes to complete all jobs. A project activity C has a duration of 3 days and two predecessors A & B. A has an EF of 10 and B an EF of 12. What is the earliest C may be completed? - CORRECT ANSWER15 Explanation: Max (10,12) + 3 = 15 A project's indirect costs are $1,000 per day. Currently there are 3 activities available to crash. All can be shortened by up to 1 day and none is on the Critical-Path. Crashing costs are: A for $800 per day. B for $1,200 per day and C for $500 per day. What should you do? - CORRECT ANSWER Do not crash any. The Critical Path is never: - CORRECT ANSWER The shortest path If staffing requirements for Saturday are met using a full-time employee (and not a part-time employee working Saturdays only), how will service capacity be affected? - CORRECT ANSWER The number of employees available will be one above the required level on every day that employee works other than Saturday Which of the following statements about queuing theory are correct? - CORRECT ANSWER- A.K. Erlang developed queuing theory while working on automatic dialing equipment. - Queuing theory is directly applicable to many service operations.

Meer zien Lees minder
Instelling
OSCM 373-
Vak
OSCM 373-

Voorbeeld van de inhoud

What is the function of a work breakdown structure?

- CORRECT ANSWER Provides the basis for detailed time and cost estimates on a
project

When using a computing algorithm to analyze large network diagrams, what are the four
pieces of information needed for each activity?
- CORRECT ANSWER Early start, early finish, late start, and late finish

When using a Gantt chart with a complex project, what tool should be used in
conjunction with the chart?
- CORRECT ANSWER Network diagram

T/F: Early start and finish times involve a forward pass, and late start and finish times
use a backward pass through the network.
- CORRECT ANSWER True

What is a network diagram, which is used by the PERT and CPM project management
techniques? - CORRECT ANSWER Diagram of project activities that shows their
sequential relationships with arrows and nodes

The slack time on the critical path is always what? - CORRECT ANSWER Zero

The critical path in a network diagram is defined as what?
- CORRECT ANSWER The longest path from start to finish which determines the
overall project duration.

If a budget was too optimistic, it was ____________ the actual project cost.
- CORRECT ANSWER lower than

What is used in AOA diagrams to clarify relationships, such as two activities that have
the same starting and ending nodes?
- CORRECT ANSWER Dummy activity

Select all of the reasons why a project manager would want to shorten the duration of a
project.
- CORRECT ANSWER- Incentive payment earned if project completion date is early
- To free up resources to work on another project
- Monetary penalty due if agreed-to schedule is exceeded

All of the following information can be produced by the network diagram computing
algorithm except which?
- CORRECT ANSWER Most expensive path

Select all of the rules project managers follow when crashing a schedule.
- CORRECT ANSWER- Crash the schedule one period at a time

,- Recalculate the critical path after each crashing
- Crash the least expensive activity on the critical path

Which of the following is calculated in a forward pass?
- CORRECT ANSWERE S = 0
ES + Activity time = EF

In critical chain project management the critical path is viewed as a what?
- CORRECT ANSWER Bottleneck

Why is slack time valuable information for project managers?
- CORRECT ANSWER Resources may be shifted to more critical activities away from
those with slack

There are many advantages to using a project management software package. Among
them are which of the following?
- CORRECT ANSWER-It automatically formats reports.
- It can generate various chart types, including basic Gantt charts.
- It enables what-if scenarios.
- It can enhance communication among team members.
- It provides a logical planning structure.
- It imposes a methodology and a common project management terminology.
- It can flag the occurrence of constraint violations.
- It can generate multiple levels of summary reports and detailed reports.

Select all of the reasons that project costs may exceed budgeted amounts.
- CORRECT ANSWER- Weather or supplier delays
- Budget too optimistic
- Rework of substandard workmanship

T/F: It is common for projects to fail, either partially or completely.
- CORRECT ANSWER True

In project management, shortening activity durations by applying additional resources to
it is called ______________.
- CORRECT ANSWER crashing

Which of the following statements about risk probability and cost are true?
- CORRECT ANSWER Probability of occurrence of a risk is highest at the start.

Why are only activities on the critical path candidates for crashing?
- CORRECT ANSWER Only the critical path directly affects the completion date

Similar to the theory of constraints, critical chain project management uses what to
support the critical path?
- CORRECT ANSWER Buffers

, What are some of the features of common project management software?
- CORRECT ANSWER- Track progress/performance of scheduled project activities
- Flag missing precedence relationships between activities
- Assign resources to project activities

Operating in an environment of uncertainty, projects are subject to what negative
outcomes?
- CORRECT ANSWER Delays, budget overruns, inability to meet technical
requirements

T/F: With proper risk management all cost, schedule and technical risks can always be
avoided on a project.
- CORRECT ANSWER False

Customers arrive at a rate (λ) of 8 per hour (arrival pattern can be described with a
Poisson distribution with a mean of 8). Service representative requires an average of 6
minutes (1/μ) to assist a customer (service time can be described with an exponential
distribution with a mean of 6).
What is the average queue length?
- CORRECT ANSWER3.2
Working (uses M/M/1 system):
Arrival Rate λ = 8 customers/hour
1/μ = 6 minutes => Service Rate, μ = 60/6 = 10 customers/hour
Lq= λ^2/(μ *(μ-λ)) = 8^2/(10*(10-8)) = 64/20 = 3.2 customers

Customers arrive at a rate (λ) of 45 per hour (arrival pattern can be described with a
Poisson distribution with a mean of 45). A service representative requires an average of
6 minutes (1/μ) to assist a customer (service time can be described with an exponential
distribution with a mean of 6). The company employs 6 service representatives. What is
the average queue length?
- CORRECT ANSWER1.265 customers
Working (M/M/S system):
λ = 45 customers/hour
1/μ = 6 minutes => μ = 60/6 = 10 customers/hour
Referring to the table with λ/μ = 45/10 = 4.5 & M=6 => Lq = 1.265 customers

Customers arrive to a concession stand at the rate of 72 per hour. Arrival rate can be
described by a Poisson distribution. The stand has 4 windows. Buying a hot dog takes
on average 3 minutes per customer and varies exponentially.
What is the maximum waiting-line length (at least) 40% of the time?
- CORRECT ANSWER2

Customers arrive at a rate (λ) of 8 per hour. Each service representative requires an
average of 6 minutes to assist a customer. The system has an average queue length of
4 customer.

Geschreven voor

Instelling
OSCM 373-
Vak
OSCM 373-

Documentinformatie

Geüpload op
8 november 2024
Aantal pagina's
16
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$18.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
janetheuri
3.0
(1)

Maak kennis met de verkoper

Seller avatar
janetheuri Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
7
Lid sinds
1 jaar
Aantal volgers
0
Documenten
517
Laatst verkocht
10 maanden geleden

3.0

1 beoordelingen

5
0
4
0
3
1
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen