Answer : D final inspection
When located in a flood hazard area , documentation of the lowest floor elevation shall
be submitted to the building official prior to which of the following inspections ?
A concrete slab inspections
B rebar inspection
C grading inspection
D final inspection
Answer: A the square footage of the structure
Which of the following information is not required to be placed on a certificate of
occupancy?
A the square footage of the structure
B the address of the structure
C the name of the building official
D the building permit number
Answer: A Qualified and reliable
The building official is authorized to accept reports from approved inspections agencies
provided they are..
A.qualified and reliable
B. Insured
C. Certified
D. Licensed
Answer: the building was sold to a new owner
Which of the following is not a valid reason to revoke a certificate of occupancy?
A was issued with incorrect information
B a portion of the building is in violation of the building code
C was issued in error
D the building was sold to a new owner
Answer : law
A building code is adopted by a jurisdiction as______
A resolution
B a standard
C a guideline
D law
Answer : 54
Window awnings installed on group r-3 structures supported only by an exterior was do
not require a building permit when projecting no more than____ inches beyond the wall.
A 54
B36
C48
D30
Answer : approved prior to the start of the system installation
, Shop drawings for the fire protection systems shall be ____
A prepared by a registered design professional
B submitted upon completion of the system installation
C approved prior to the start of the system installation
D approved prior to the completion of the system installatio
Answer : permit application and permit
What are the two most important documents a code official has to determine what a
contractor is doing at the job site ?
A permit and plans
B plans and inspection card
C permit application and permit
D permit and inspection card
Answer : the issuance of the building permit
What is considered the most important step in the enforcement and administration of
building codes ?
A verifying proper licensing
B the review of the construction documents
C the inspections
D the issuance of the building permit
Answer : grade
The lowest point of elevation of the existing surface of the ground , within the area
between the building and a line 5ft from the building is known as the ____
A grade level
B building elevation
C grade plane
D grade
Answer : name of general contractor
All of the following is required to be on a permit application EXCEPT of which of the
following ?
A valuation of work
B use and occupancy
C name of the general contractor
D description of work
Answer : r-3
Apartment houses are permitted in a(n)___ doing district
A c-1
B r-1
C r-3
D r-2
Answer : applicable governing body
Who shall appoint the members of the board of appeals ?
A applicable governing body
B zooming official
C city manager
D building official