Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

NERC TEST 3 QUESTIONS AND ANSWERS A+ GRADED. Buy Quality Materials!

Beoordeling
-
Verkocht
-
Pagina's
23
Cijfer
A+
Geüpload op
20-11-2024
Geschreven in
2024/2025

NERC TEST 3 QUESTIONS AND ANSWERS A+ GRADED. Buy Quality Materials! A CPS1 violation is an indication that : A BA's ACE is hindering frequency . A BAS ACE is helping frequency A BA's Frequency Bias is set too high . A BA is not meeting its L10 . A BA's ACE is hindering frequency . A Balancing Authority has a normal generation capacity of approximately 9400 MW and its most severe single contingency is an 800 MW coal fired steam unit . At 1430 , with an ACE value of 20 MW , a 600 - MW generator trips off line as the result of a generator differential . This resulted in a large negative ACE for the Balancing Authority . What value must the ACE return to and in what time frame to avoid a DCS violation ? Must return ACE to 20 MW in 15 minutes . Must return ACE to 0 MW in 10 minutes . This does not constitute a reportable disturbance . Must return ACE to 0 MW in 15 minutes . This does not constitute a reportable disturbance . The DCS criteria applies to a sudden loss of generation that exceeds 80 % of the Balancing Authorities most severe single contingency , or in this case 80 % of 800 MWs which is 640 MWs . Since only 600 MWs were lost , the DCS criteria does not apply . However , the BA should return ACE as quickly as possible . Balancing Authority A is currently reading a system frequency of 59.98 Hz . Its Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +100 MW . If Balancing Authority A's frequency bias setting is 100 MW / 0.1 HZ , what is ACE ? 20 -20 0 2 -20 On problems like this actual do the ace equation Balancing Authority A is currently reading a system frequency of 59.95 Hz . Its Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +120 MW . If Balancing Authority A's frequency bias setting is -100 MW / 0.1 Hz , Balancing Authority A's AGC is pulsing its generators to ___________ Remain at current MW output level Increase MW output Decrease MW output Increase excitation on the field windings Take the two portions of the ACE equation separately . 1 ) Frequency is low which contributes to a negative ACE . 2 ) Actual Interchange is less than scheduled which also causes negative ACE . Without even calculating the ACE value , it is evident that ACE will be negative and therefore AGC should be pulsing generators to increase their MW output Balancing Authority " A " is importing 225 MWs , and is only scheduled to import 200 MWs . The BA's Bias Setting is 200 MWS / .1 Hz and frequency is 59.99 Hz . What does ACE indicate ? 45 MW over - generating 20 MW over - generating 20 MW under - generating 45 MW under generating 45 MW under generating Plug into the ace equation! A Balancing Authority's inadvertent accumulation reflects over - generation during on peak hours . When system load is decreasing , what actions could a Balancing Authority system operator take to limit additional on peak inadvertent accumulation 1. Decrease transactions into their system 2. Increase transactions into their system 3. Decrease generation 4. Increase generation 02 and 3

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

NERC TEST 3 QUESTIONS AND ANSWERS A+
GRADED. Buy Quality Materials!

A CPS1 violation is an indication that :

A BA's ACE is hindering frequency .

A BAS ACE is helping frequency

A BA's Frequency Bias is set too high .

A BA is not meeting its L10 .
A BA's ACE is hindering frequency .
A Balancing Authority has a normal generation capacity of approximately 9400
MW and its most severe single contingency is an 800 MW coal fired steam unit .
At 1430 , with an ACE value of 20 MW , a 600 - MW generator trips off line as the
result of a generator differential . This resulted in a large negative ACE for the
Balancing Authority . What value must the ACE return to and in what time frame
to avoid a DCS violation ?

Must return ACE to 20 MW in 15 minutes .

Must return ACE to 0 MW in 10 minutes .

This does not constitute a reportable disturbance .

Must return ACE to 0 MW in 15 minutes .
This does not constitute a reportable disturbance .


The DCS criteria applies to a sudden loss of generation that exceeds 80 % of the
Balancing Authorities most severe single contingency , or in this case 80 % of 800 MWs
which is 640 MWs . Since only 600 MWs were lost , the DCS criteria does not apply .
However , the BA should return ACE as quickly as possible .
Balancing Authority A is currently reading a system frequency of 59.98 Hz . Its
Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +100 MW
. If Balancing Authority A's frequency bias setting is 100 MW / 0.1 HZ , what is
ACE ?

20

-20

0

,2
-20

On problems like this actual do the ace equation
Balancing Authority A is currently reading a system frequency of 59.95 Hz . Its
Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +120 MW
. If Balancing Authority A's frequency bias setting is -100 MW / 0.1 Hz , Balancing
Authority A's AGC is pulsing its generators to ___________

Remain at current MW output level

Increase MW output

Decrease MW output

Increase excitation on the field windings
Take the two portions of the ACE equation separately . 1 ) Frequency is low which
contributes to a negative ACE . 2 ) Actual Interchange is less than scheduled which also
causes negative ACE . Without even calculating the ACE value , it is evident that ACE
will be negative and therefore AGC should be pulsing generators to increase their MW
output
Balancing Authority " A " is importing 225 MWs , and is only scheduled to import
200 MWs . The BA's Bias Setting is 200 MWS / .1 Hz and frequency is 59.99 Hz .
What does ACE indicate ?

45 MW over - generating

20 MW over - generating

20 MW under - generating

45 MW under generating
45 MW under generating

Plug into the ace equation!
A Balancing Authority's inadvertent accumulation reflects over - generation
during on peak hours . When system load is decreasing , what actions could a
Balancing Authority system operator take to limit additional on peak inadvertent
accumulation
1. Decrease transactions into their system
2. Increase transactions into their system
3. Decrease generation
4. Increase generation

02 and 3

, 01 and 4

2 and 4

1 and 3
1 and 3
The Frequency Response Measure ( FRM ) of a Balancing Authority is determined
by using actual data from past frequency events . What provides Interconnection
Frequency support ?

All generators in North America will increase generation according to their size .

All generators ' automatic generation control response to ACE .

Generator governor response within the Interconnection resulting in an increase
of generation .

Each generator has a fixed amount of support to provide regardless of status and
size .
Generator governor response within the Interconnection resulting in an increase of
generation .
At the end of the business day , two adjacent Balancing Authorities must agree
with which of the below actual operating values regarding Inadvertent
Interchange ?

1. The hourly integrated values of Net Interchange Schedule .
2. The hourly values of each Interchange Transaction .
3. The hourly integrated megawatt values of individual interconnecting the lines .
4. The hourly integrated values of Net Actual Interchange .

1 , 2 , 3 and 4

1 and 4

2 and 3

2 and 4
1 and 4
Which of the following are true about system frequency ?

lt is related to the speed of the generators tied to the system .

lt is an indication of generation to load demand balance .

It is measured in Hertz .

Geschreven voor

Vak

Documentinformatie

Geüpload op
20 november 2024
Aantal pagina's
23
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$10.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TopGradeSolutions Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
95
Lid sinds
2 jaar
Aantal volgers
9
Documenten
13297
Laatst verkocht
4 dagen geleden
TOPGRADESOLUTIONS

Here we offer revised study materials to elevate your educational outcomes. We have verified learning materials (Research, Exams Questions and answers, Assignments, notes etc) for different courses guaranteed to boost your academic results. We are dedicated to offering you the best services and you are encouraged to inquire further assistance from our end if need be. Having a wide knowledge in Nursing, trust us to take care of your Academic materials and your remaining duty will just be to Excel. Remember to give us a review, it is key for us to understand our clients satisfaction. We highly appreciate clients who always come back for more of the study content we offer, you are extremely valued. All the best.

Lees meer Lees minder
4.9

171 beoordelingen

5
159
4
7
3
4
2
0
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen