You are performing the Plan Risk Responses process for your manufacturing
project and encounter a critical risk that may have a high impact on the project
completion. All of the following are valid responses to this new risk except?
Conducting Bidder Conferences
You are currently performing the Plan Quality process for your construction
project. You are required to prepare the process improvement plan along with the
quality management plan for your project. You intend to use the Six Sigma
methodology to help you in your process improvement. Which of the following
should you choose for your process improvement plan?
DMAIC - Define, Measure, Analyze, Improve, Control
Which of the following statements regarding the work breakdown structure (WBS)
is incorrect?
The WBS contains componenets representig higher levels of scope decomposition
called work packages
You have just started managing a project to produce a guidance system for a
communications satellite. According to the previous project manager, the project
team was in the performing stage and smoothly completing the project activities.
During your first week as the project manager you decide to change a few of the
project procedures to make them more efficient. You also determined after
, meeting with each of the project team members that the project team is actually
in serious conflict. What is the most likely reason for the project team's current
behavior?
The replacement of the project manager has moved the project team back to the
storming stage
If EV = $100, AC = $90, PV = $110 and BAC = $400, how much is the Cost Variance
of a project?
$10
Which of the following statements is correct regarding the Close Project or Phase
process?
The close project or phase process is always the last process that is performed during
the project
In one of your presentations to your project sponsor you mentioned the Code of
Accounts. She is unfamiliar with the term and asks for clarification. Which of the
following would you use to explain the Code of Accounts?
Work Breakdown Structure
The total authorized budget for your IT project is $160,000 and management
reserves is $20,000. You want to measure cost performance to see how the
project is doing. In this context, the cost performance is against measured which
of the following budget amounts?
$140,000
You are managing a project to create a new brand of smart motorized wheelchairs
for the orthopedic ward at a neraby medical center. You have have just calculated