. The scope of the professional CM's basic and
invariable role and
responsibility is to serve the needs of
the owner.
True. False -Answer:
(TRUE)
During the CM selection process, which of the following
statements is true?
a. The parties should have a clear understanding of the scope of
CM services required and what form of CM agreement is
proposed for use during the engagement.
b. The owner should consider the cost of CM services only after
the
establishment of the technical requirements and after careful
consideration of the
CM's qualifications, related experience and proposed staffing
plan
,c. The proposed CM agreements should clearly define the risks
authority assumed by the CM, as distinguished from those
retained by the owner. d. All of the above. -Answer: All of the
above.
There are no accepted industry-wide standards or guidelines for
determining
what is considered to be reasonable and fair compensation
for construction
management
services.
True. False -Answer: (
FALSE)
A CM's role and responsibilities are governed solely by the
Owner/CM
1. Agreement.
True False -Answer: (TRUE)
There are two basic forms of CM, agency and at-risk. Each
form provides for the basic services of construction
management practice. However, there are some key
differences. Which of the following do not apply to both CM
forms?
a. Both forms provide advice to the owner on
constructability, budget and the schedule.
,b. Both require that the liabilities and risks assumed by the
parties be clearly understood, coordinated, and stated in the
respective contracts.
c. Both forms allow the CM to function in an advisory role for
the entire engagement of the CM.
d. Services can vary based on the contractual relationships of
the parties and the risks that are assumed. -Answer: Both forms
allow the CM to function in an advisory role for the entire
engagement of the CM.
Construction management had its beginnings in the early to mid-
1960's. Which
of the following factors contributed to the initial use of this
delivery system?
a) The need to reduce the overall time and cost associated with
project delivery.
b) The increasing cost of money and the unpredictability of
project funding
streams.
c) The changing role of the general contractor and the
increasing numbers of
specialty trade
contractors.
d) All of the above. -Answer: All of the
above.
, The General Services Administration was the first federal
agency to use
construction management. -
Answer: (TRUE)
. The General Services Administration, the Department of
Health, Education
and Welfare (now HHS), and the Veterans Administration
ran into similar
difficulties in the use of construction management. Which
of the following
was/were common problems for all three
agencies?
a) Funding restrictions
b) Claims
c) Change conditions
d) All of the above -Answer: All of the above
CMAA was formed and incorporated 1982 with its primary focus
being the growth and development of the construction
management profession. -Answer: (TRUE)
The CMAA Construction Management Standards of Practice is
intended as a guide to the range of services that constitute
professional construction management. They seek to meet the
documented need for definitions of what construction