CDT COMPREHENSIVE EXAM AND PRACTICE EXAM NEWEST
2025 ACTUAL EXAM COMPLETE 250 QUESTIONS AND CORECT
DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED
A+
Publication in public documents such as a local newspaper that a
Advertisement to bid
project is open to qualified bidders
P rovisions can prevent a single party from initiating litigation and
Alternative dispute
provide a suitable method to economically and expeditiously
resolution
addressing disputes
Products do not need to be evaluated according to each and every
Applicable Criteria for
product criterion known, but only those that apply to the specific
Evaluation
project
Concepts are evaluated in detail: cost analysis, impact on other work,
Analytical/Development
schedule impacts, system performance, plan of implementation,
Phase
recommendations
Public entities often require archeological surveys before
construction can start. Any costal site or river floodplain and many
Archeological Surveys urban sites may have historic or prehistoric artifacts that require the
input of an archeologist; other parts of the country may have artifacts
from Native Americans
A prominent method for assessing the environmental performance of
Assessing System new and existing facilities is the USGBC’s LEED, Green Building Rating
Sustainability System, which sets a standard for developing high-performance
sustainable buildings, the core of which is its accreditation system
Assessing Product Determining whether a product or facility is sustainable,requires a life
Sustainability cycle assessment by a qualified project participant. According to the
, BEESmodel, the life cycle of a product is a 50 year period, the stages
of which are as follows: Raw materials acquisition, Product
manufacturer, Transportation, Installation, Operation, Maintenance
Characteristic of performance. There are three essential
Attributes
characteristics of an attribute: Requirements, Criteria, Tests
Attribute categories include:, General considerations, Physical
Attribute Categories
properties, Performance, Sustainability, Safety and protection,
for Evaluation
Manufacturers, Installers, Cost, Maintenance
Federal, state, county, and city authorities oversee the safety and
welfare of the public they serve. In doing so, they verify that the code
and ordinance requirements have been met. The authorities having
Authorities Having jurisdiction usually performs reviews of the contract documents
Jurisdiction before issuing permits. They verify that the regulatory requirements
are being met by performing building, mechanical, electrical,
elevator, fire, life safety, health, zoning, accessibility, and critical
structural inspections at the project site.
Basis of Payment Lump sum, Unit price, Cost Plus, cost Plus with guaranteed maximum
The National Institute of Standards Technology (NIST) a branch of the
US Department of Commerce, implemented its Building for
Environmental and Economic Sustainability (BEES) program which is a
BEES model for evaluating environmentally preferable building products.
The BEES project aims at implementing a system for choosing
products which are the best balance between environmental and
economic considerations
Bid Bond The purpose of the bid bond is to protect the owner from losing the
benefit of an accepted bid. Issuance of a bid bond commits the
bidder to enter into a contract and, if required, provide performance
and payment bonds. The bid bond is provided by the bidder at the
time of the bid and is submitted with the bid. The bid bond provides
for a penal amount expressed either in dollars or as a percentage of
the total amount of the bid. In the event that the selected bidder fails
or refuses to enter into a contract for the price of the bid, the surety
is obligated to pay the owner’s damages, up to the penal amount of
, the bid bond.
Receives subcontractor bids for identified units of work. The units of
work are usually significant parts of the total project. These sub-bids,
Bid Depository
depending on location, are then either analyzed by the client agency
with the selected sub-bids assigned to the general contractor
Guaranties that if a bid is accepted within the specified time, the
bidder will enter into a formal agreement with the owner (usually 30
to 90 days from the opening of the bids) and will furnish the required
Bid Security
construction performance and payment bonds. The purpose of the
bid security is to compensate the owner for damages incurred if the
selected bidder does not accept the contract award
Stage in the facility life cycle that allows the prospective contractor to
examine bidding documents, visit the site, request clarifications and
Bidding / Purchasing / interpretations, propose substitutions, and finally, prepare a bid or
Negotiating / Procurement price for executing the work. Acceptance of the contractor’s bid or
negotiated sum and other conditions will result in award of contract
and commencement of work
A policy separate from a builder’s risk policy. Insures against loss
Boiler and Machinery
resulting from accidents to boilers and pressure vessels identified in
Insurance
the policy, including damage to others property
Cost control and budgeting rely on accurate accounting. The goal of
operations and maintenance budgeting is to ensure the most
Cost Control
effective and efficient use of resources toward meeting the
company’s stated facility objectives
Provide a hierarchical organization for describing drawing layers.
Theuser can identify or name on the basis of the level of detail
CAD Layer Guidelines provided in each drawing layer. The guidelines define the four data
fields within layer names: Discipline designators, Major group, Minor
groups, Status
Change directives are used in absence of an agreement between the
Change Directives owner and the contractor on the terms of a change order or when
the value of a change cannot be determined until after the work is