Which of these documents, might we find in the Project Manual
but they are not contract documents?
A. The Agreement
B. Procurement Requirements
C. Addendum
D. Supplemental Conditions B
Before a model building code can become the building code for
a jurisdiction, it has to be adopted by?
A. Authority Having Jurisdiction
B. State Government
C. Building Inspector
D. International Organization for Standardization A
The Construction Manager is hired by this entity?
,2
A. General Contractor
B. Owner
C. A/E
D. Contract Administrator B
The parties to the Construction Agreement are?
A. General Contractor, Subcontractor, and Construction
Manager
B. A/E, General Contractor, and Contract Administrator
C. Building Official and General Contractor
D. Owner, Contractor, and A/E D
The organization responsible for the General Conditions known
as 201 are?
A. DBIA
B. AGC
C. AIA
D. CSI C
When there is a dispute between the specifications and the
drawings, what is the proper way to settle the dispute?
A. The drawings have priority
B. The A/E should interpret
C. The specifications
,3
D. Arbitration B
A subcontractor is obligated to the prime contractor in the
same manner as the prime contractor is obligated to the:
A. Architect
B. Owner
C. Material Supplier
D. Principal in Charge B
The requirements of the General Conditions can be modified or
expanded to accommodate specific project conditions, owner's
requirements, or unusual aspects relating to the roles, rights,
duties, and responsibilities of the parties to the contract for
construction, in this document:
A. Contract Modifications
B. Supplemental Conditions
C. Addendum
D. Consensus Documents B
Which of the following are not legal binding construction
documents?
A. General Conditions
B. Specifications
C. Preliminary Project Description
D. Addendum C
, 4
This document states that the Contractor shall review, approve,
and submit to the Architect, shop drawings, product data,
samples, and similar submittals required by the contract
documents. It also states that the Architect will review and
approve or take other appropriate action upon the Contractor's
submittals:
A. Construction Agreement
B. Field Order
C. General Requirements
D. AIA A201 D
Division 01 sections apply broadly to the execution of the work
of all the other sections of the specifications. In addition, they
expand on certain administrative and procedural provisions of
the:
A. Drawings
B. Construction Agreement
C. Conditions of the Contract
D. Procurement Documents C
Defined as the written and graphic documents prepared or
assembled by the A/E for communicating the project design for
construction and administering the construction contract:
A. Construction Documents
B. Plans