1. EQ's social awareness component involves knowing one's social status.
2. One component of a person's EQ is their degree of self-regulation.
3. A person's relationship management is the least-important component of their
EQ.
4. EQ has proven to be less important in most people's career success than their
IQ.
You have completed this earned value chart, which shows your project's planned
value (PV),earned value (EV), and actual cost (AC). What does this chart tell you
about your project?
1. It is under budget and ahead of schedule.
2. It is over budget and on schedule.
Your sponsor wants you to create a new delivery system. After you ask why the
new system is needed and determine what is wrong with the current system, you
are then able to create which key document?
1. the project analysis
2. the problem statement
3. the project questionnaire
4. the test hypothesis
What statement about rough order of magnitude (ROM) budget estimates is
false?
1. ROMS are built at the project initiation stage.
2. ROMs should have a variance of minus 10% to plus 15% of the actual cost.
3. ROMs provide an initial cost estimate to determine whether a project is viable.
4. ROMs are usually based on knowledge of similar projects.
Project Zebra has two primary risks. The first is that a competitor will create a
superior product. The second is that an equipment breakdown will cause delays.
What is true about these two risks?
1. Both risks are variability risks.
2. The first risk is a variability risk, and the second risk is an ambiguity risk.
3. The first risk is an ambiguity risk, and the second risk is a variability risk.
4. Both risks are ambiguity risks.
Sanjit's virtual IT team has been delivering software components faster than
planned, but some team members disagree on a key quality issue. How can Sanjit
best handle this conflict?
1. Hold a video conference with all the team members.
2. Send an email outlining the conflict to all team members.
3. Set a deadline for the team to resolve the issue.
, 4. Have a one-on-one conversation with each team member.
You want to account for the time it will take for concrete to cure before framing
can start on a construction project. What is the best way to model this on the
critical path?
1. Indicate the break between the links with a modified start-to-start dependency.
2. Add a new activity that reflects the concrete curing time.
3. Add lag to the dependencies between the two tasks.
4. Link the two tasks with a finish-to-finish dependency.
On a Gantt chart, what do arrows between bars indicate?
1. activity dependencies
2. completed deliverables
3. positive lags
4. PERT triggers
Stefan wants an 86% probability that the actual hours needed to finish his project
will be lessthan or equal to the estimated hours. For his estimate, what value on a
bell curve should Stefan select?
1. the value of the best-case scenario multiplied by two, divided by the worst-case
scenario
2. the value halfway between the best-case number of hours and the average
number of hours
3. the value halfway between the average number of hours and the worst-
case number of hours
4. the average number of hours, as represented at the peak of the bell curve
Using the DISC personality profile tool, you discover that your primary personality
type is "I." What does this tell you about yourself?
1. You are an intimidator, and this often discourages team members from
approaching you.
2. You are intense, and you often make your work a top priority in life.
3. You are an influencer, and you tend to be a good motivator and problem-
solver.
4. You are an innovator, and you can come across too forcefully even though you
are creative.
Fatima is a project manager. She lists the project tasks and places them in the
correct sequence.To build the project schedule, what is her next step?
1. Assign resources to all work packages.
2. Include dependencies for all tasks.
3. Add contingency buffers to the milestones.
4. Calculate the resources required for all summary tasks.