Which of the following OSHA regulations govern suspended personnel platforms? - ANSWER ✔✔-
OSHA 1926.1431
According to ASME B30.3 The prohibited zone for power lines that are 60 kV is - ANSWER ✔✔-15 ft
According to ASME B30.3, load hoist rotation resistant wire rope has a design factor of - ANSWER ✔✔-5
to 1
According to ASME B30.3 when Lifting a suspended personnel platform design factor for the rigging
hardware is - ANSWER ✔✔-5 to 1
According to ASME B30.3 Load hoist ropes that are not rotation resistant must have a design factor of -
ANSWER ✔✔-5 to 1
The OSHA construction standard for rigging equipment is - ANSWER ✔✔-1926.251
According to ASME B30.3 on who's recommendations should a preventative maintenance program be set
up? - ANSWER ✔✔-Crane manufacturer
When using cable or nylon spreaders it is important to remember: - ANSWER ✔✔-The lower the spreader
angle the greater the tension
According to OSHA when testing a man basket how long must the test pick be maintained? - ANSWER
✔✔-5 minutes
Created by ©EmilyCharlene 2025. All rights reserved.
, 2|Page
According to ASME B30.3 What is the minimum pitch diameter for load hoisting sheaves? - ANSWER
✔✔-Not less than 18 times rope diameter
According to ASME B30.3 what is the minimum pitch diameter for load block sheaves? - ANSWER ✔✔-
Not less than 16 times rope diameter
According to ASME B30.3 what is the minimum pitch diameter for boom hoist sheaves? - ANSWER ✔✔-
Not less than 15 times rope diameter
According to OSHA when lifting personnel the cranes hook must be the type that - ANSWER ✔✔-Can be
closed and locked
According to OSHA when working over water with a man basket are the people inside required to wear
a belt/harness? - ANSWER ✔✔-No harness or belt required
According to ASME B30.3 when working near powerlines where should caution stickers be installed? -
ANSWER ✔✔-Operator station and at the base of the crane
According to OSHA a frequent inspection is: - ANSWER ✔✔-Daily to monthly
According to OSHA a periodic inspection is: - ANSWER ✔✔-Monthly to annually
Cranes idle for more than six months must have inspections performed: - ANSWER ✔✔-Frequent and
periodic
Cranes idle for less than six months must have inspections performed: - ANSWER ✔✔-Frequent
Cranes lifting personnel platform must have the platform and rigging inspected: - ANSWER ✔✔-Prior to
each shift
Crane hooks must not be twisted in excess of: - ANSWER ✔✔-10 degrees
A Crane hook's throat must not exceed: - ANSWER ✔✔-15% of its original size