A likely precipitation event is any weather pattern that is forecasted to have a __% or
greater probability of producing precipitation in the project area.
a. 10
b. 25
c. 50
d. 75
e. 99 - CORRECT ANSWER: C
A QSP is responsible for:
a. Day to day implementation, inspections, and observations
b. Amending the SWPPP as required
c. Developing and certifying the SWPPP
d. Certifying reports in SMARTS - CORRECT ANSWER: A
A storm that produces ½ inch or more of precipitation, with a 48 hour or greater period
between rain events is a/an...
a. Qualifying rain event
b. Extended storm event
c. Inactive storm event
d. Unsafe monitoring event - CORRECT ANSWER: A
A temporary or permanent structural BMP that directs concentrated flows away from
disturbed areas and prevents erosion is...
a. erosion control
,b. run on/ run off control
c. sediment control - CORRECT ANSWER: B
Acceptable methods to demonstrate final stabilization include:
a. 50%vegetative coverage
b. 100% vegetative coverage
c. RUSLE 2 method - CORRECT ANSWER: C
Activities under the CGP include:
a. Routine maintenance to maintain original line and grade, hydraulic capacity, or
original purpose of the facility.
b. Disturbances to land surfaces solely related to agricultural operations.
c. Clearing and grading 2 acres of land
d. Discharges of storm water from areas on tribal lands. - CORRECT ANSWER: C
All NAL data must be uploaded within ___ after NAL exceedance has been identified
a. 24 hours
b. 1 week
c. 10 days
d. 2 weeks - CORRECT ANSWER: C
Certain non-storm water discharges may be necessary for the completion of
construction projects. Therefore the General Permit authorizes such discharges
provided they meet the following conditions except:
a. Meet the NALs for pH and turbidity
b. Not cause or contribute to a violation of water quality standards
c. Comply with BMPs as described in the SWPPP
d. Be infeasible to eliminate
e. Causes or threatens to cause pollution, contamination, or nuisance - CORRECT
ANSWER: E
, Hydrologic source controls are a design technique that minimize and/or slow the rate of
stormwater runoff from the site. Examples include:
a. Reduction of pervious surfaces
b. Use of landscaping as a storm drain treatment feature
c. Drain rooftop downspouts to impervious areas
d. Stormwater treatment facility - CORRECT ANSWER: B
If the R Factor is ____, you can apply for the Erosivity Waiver.
a. 1
b. Less than 1
c. 5
d. Less than 5 - CORRECT ANSWER: D
NEL Violation Reports must be submitted to State Board within 24 hours after
exceedance has been identified. NEL's are only subject to:
a. Risk Level1
b. Risk Level 2
c. Risk Level 3
d. ATS Sites only - CORRECT ANSWER: D
Once identified, dischargers shall begin implementing repairs or design changes to
BMPs:
a. Immediately
b. Within24 hours
c. Within48 hours
d. ASAP, but not more than 72 hours - CORRECT ANSWER: D
Permit Registration Documents (PRDs) shall consist of all of the following except: