Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CDS - Exam 1 Practice Questions and Answers 100% Pass

Beoordeling
-
Verkocht
-
Pagina's
9
Cijfer
A+
Geüpload op
22-12-2024
Geschreven in
2024/2025

CDS - Exam 1 Practice Questions and Answers 100% Pass Labor and material payment bonds provide the necessary protection on public projects - TRUE Miller act corresponds with what.? - Labor and material payment bond Architects should not advise owners and the legal sufficiency of required affidavits, waivers, or releases of liens. - TRUE Liens are not permitted on public projects. - TRUE Architect must review, approve, and promptly submit shop drawings required by the contract documents. - TRUE An architect approved shop drawings which deviated from the contract documents. - Changes in contract drawings must be submitted in writing to architect before becoming affective, not equal to revisions within shop drawings. Who is responsible for errors and omissions in shop drawings? - General Contractor Revisions not requested by the architect on resubmitted shop drawings don't require architect's approval? - FALSE A contractors stamp of approval on shop drawings means that the contractor has already determined all criteria related thereto. - FALSE AIA document B101 is used to outline the architects service obligations? - TRUE 2 | P a g e Created by Katelyn Whitman © 2025, All Rights Reserved. 100% PASS GUARANTEE The architects responsibilities are re-stated within the AIA General Conditions Doc A201. - TRUE Contractors may not know what services the architect is obligated to perform if what document is not part of the contract documents. - AIA Document B101 In review of shop drawings the general conditions Document A201 clearly states? - Matters outside the scope of the design concept and the contract documents are not reviewed. If an architect had performed their services using stipulations of AIA documents A201 & B141 within a ______ there should be no concern about professional liability. But general liability is different. - Standard of care Calendar days - 7 / Week Liquidated damages is a provision included in the? - Owner-contract

Meer zien Lees minder
Instelling
CDS - Certified Disability Specialist
Vak
CDS - Certified Disability Specialist

Voorbeeld van de inhoud

1|Page




CDS - Exam 1 Practice Questions and
Answers 100% Pass

Labor and material payment bonds provide the necessary protection on public projects - ✔✔TRUE


Miller act corresponds with what.? - ✔✔Labor and material payment bond


Architects should not advise owners and the legal sufficiency of required affidavits, waivers, or releases

of liens. - ✔✔TRUE


Liens are not permitted on public projects. - ✔✔TRUE


Architect must review, approve, and promptly submit shop drawings required by the contract

documents. - ✔✔TRUE


An architect approved shop drawings which deviated from the contract documents. - ✔✔Changes in

contract drawings must be submitted in writing to architect before becoming affective, not equal to

revisions within shop drawings.


Who is responsible for errors and omissions in shop drawings? - ✔✔General Contractor


Revisions not requested by the architect on resubmitted shop drawings don't require architect's approval?

- ✔✔FALSE


A contractors stamp of approval on shop drawings means that the contractor has already determined all

criteria related thereto. - ✔✔FALSE


AIA document B101 is used to outline the architects service obligations? - ✔✔TRUE




Created by Katelyn Whitman © 2025, All Rights Reserved. 100% PASS GUARANTEE

, 2|Page


The architects responsibilities are re-stated within the AIA General Conditions Doc A201. - ✔✔TRUE


Contractors may not know what services the architect is obligated to perform if what document is not

part of the contract documents. - ✔✔AIA Document B101


In review of shop drawings the general conditions Document A201 clearly states? - ✔✔Matters outside

the scope of the design concept and the contract documents are not reviewed.


If an architect had performed their services using stipulations of AIA documents A201 & B141 within a

______ there should be no concern about professional liability. But general liability is different. -

✔✔Standard of care


Calendar days - ✔✔7 / Week


Liquidated damages is a provision included in the? - ✔✔Owner-contractor agreement. Document A101.


An amount of money stipulated in the contract that is chargeable against the contractor is reimbursement

for damages suffered by the owner because the contractors failure to fulfill his or her contractual

obligation's. - ✔✔Liquidated damages


What clause should be used when a slight delay in schedule can cause a breach of contract? - ✔✔Time is

of the essence


CPM is superior to a Bar Chart because it shows durations, sequences and relationships to other

activities. - ✔✔TRUE


And small projects what type of progress schedule should be used? - ✔✔Bar chart


And larger complex projects what type of progress schedule should be used? - ✔✔Critical path method

CPM


How many days the contractor have to notify the architect in conditions of force majeure? - ✔✔21 days




Created by Katelyn Whitman © 2025, All Rights Reserved. 100% PASS GUARANTEE

Geschreven voor

Instelling
CDS - Certified Disability Specialist
Vak
CDS - Certified Disability Specialist

Documentinformatie

Geüpload op
22 december 2024
Aantal pagina's
9
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$12.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
KatelynWhitman West Virginia University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1184
Lid sinds
3 jaar
Aantal volgers
483
Documenten
42165
Laatst verkocht
23 uur geleden
GOLDEN QUILL NURSING LIBRARY.

Golden Quill Nursing Library: Mastering Nursing Through Questions, Answers & Expert Rationales.

3.6

252 beoordelingen

5
103
4
41
3
54
2
20
1
34

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen