Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

DBIA TEST EXAM NEWEST 2024/2025 COMPLETE QUESTIONS AND CORRECT VERIFIED ANSWERS| WELL GRADED A+|| LATEST UPDATE

Beoordeling
-
Verkocht
-
Pagina's
11
Cijfer
A+
Geüpload op
24-12-2024
Geschreven in
2024/2025

DBIA TEST EXAM NEWEST 2024/2025 COMPLETE QUESTIONS AND CORRECT VERIFIED ANSWERS| WELL GRADED A+|| LATEST UPDATE Project Delivery System - CORRECT ANSWERS-How team members are organized, establishes when parties engage, determines roles of parties, and determines sequence of design, procurement, and construction (db, cmar, dbb) Procurement Method - CORRECT ANSWERS-how team members are selected (QBS, best value, low price, sole source) contracting approach - CORRECT ANSWERS-how team members are paid (fp, gmp, cost reimbursement, target price, unit price) Design-Bid-Build (DBB) - CORRECT ANSWERS-linear, sequential process, A/E selected on qualifications, GC selected on low price, design is fully completed without input from GC, A/E acting in owner's interests, with a historically strong bond, process is well-established and understood construction manager at risk - CORRECT ANSWERS-similar org structure to DBB, construction manager selected by QBS or best value, contractor provides precon services, negotiated gmp contracting approach, open book estimating process, potential to fast track project, construction cost determined before design completed, potential issues over what is reasonably inferable from gmp design documents Design-Build - CORRECT ANSWERS-The owner contracts with one entity (a person or firm) to provide both design and construction services, designer and contractor have a direct contractual relationship, selected by QBS or best value, wide spectrum of contracting approaches and organizational structures, single point responsibility, owner does not manage designer, owner exposure to claims is significantly reduced engineer procure construct (epc) - CORRECT ANSWERS-similar to design build, in industrial and power generation sectors, systems and performance testing are central to scope, contractor will typically perform engineering with its in-house staff, owner has need for single point responsibility, contracts include plant and process performance guarantees, contract items include performance and schedule liquidated damages and limitations of liability

Meer zien Lees minder
Instelling
DBIA TE
Vak
DBIA TE

Voorbeeld van de inhoud

DBIA TEST EXAM NEWEST 2024/2025
COMPLETE QUESTIONS AND CORRECT
VERIFIED ANSWERS| WELL GRADED
A+|| LATEST UPDATE
Project Delivery System - CORRECT ANSWERS-How team members are organized,
establishes when parties engage, determines roles of parties, and determines sequence
of design, procurement, and construction (db, cmar, dbb)

Procurement Method - CORRECT ANSWERS-how team members are selected (QBS,
best value, low price, sole source)

contracting approach - CORRECT ANSWERS-how team members are paid (fp, gmp,
cost reimbursement, target price, unit price)

Design-Bid-Build (DBB) - CORRECT ANSWERS-linear, sequential process, A/E
selected on qualifications, GC selected on low price, design is fully completed without
input from GC, A/E acting in owner's interests, with a historically strong bond, process is
well-established and understood

construction manager at risk - CORRECT ANSWERS-similar org structure to DBB,
construction manager selected by QBS or best value, contractor provides precon
services, negotiated gmp contracting approach, open book estimating process, potential
to fast track project, construction cost determined before design completed, potential
issues over what is reasonably inferable from gmp design documents

Design-Build - CORRECT ANSWERS-The owner contracts with one entity (a person or
firm) to provide both design and construction services, designer and contractor have a
direct contractual relationship, selected by QBS or best value, wide spectrum of
contracting approaches and organizational structures, single point responsibility, owner
does not manage designer, owner exposure to claims is significantly reduced

engineer procure construct (epc) - CORRECT ANSWERS-similar to design build, in
industrial and power generation sectors, systems and performance testing are central to
scope, contractor will typically perform engineering with its in-house staff, owner has
need for single point responsibility, contracts include plant and process performance
guarantees, contract items include performance and schedule liquidated damages and
limitations of liability

, Multiple Prime Contracting - CORRECT ANSWERS-owner contracts with multiple trade
contractors, attributes are typically similar to dbb, owner's ability to schedule and
coordinate the work

Integrated Project Delivery (IPD) - CORRECT ANSWERS-multi-party agreement - all
parties equal, QBS procurement and target pricing contract approach, private sector
use (limited at this time), key: owner's ability to accept risk

public-private partnership (p3) - CORRECT ANSWERS-Instead of government building
and maintaining major infrastructure (such as highway, water treatment plant), build and
maintenance is outsourced to a private company. Opposed by public sector unions. this
is not considered a delivery system but its underlying approaches are delivery systems
and typically use DB. multiple procurement and contracting approaches

shift left - CORRECT ANSWERS-intense efforts to establish scope early in the process;
drives early team formation to include key trade subcontractors; can enable big
decisions to be made early, affect project outcomes at lowest cost, establish a need for
co-location and collaboration, and compress time during concurrent design and
construction

traditional design build - CORRECT ANSWERS-typically two-phase best value
procurement with lump sum contract; owner defines project requirements and scope of
prescriptive work; use of performance-based technical requirements with limited
prescriptive specifications

progressive design build - CORRECT ANSWERS-design and price are progressively
developed after the design-builder is under contract; final project cost and schedule
commitment is not established as part of the selection process; two phases: preliminary
services and final design and construction services

criteria documents - CORRECT ANSWERS-describe the end result

bridging documents - CORRECT ANSWERS-prescribes how to achieve the end result

design bid build paradigm - CORRECT ANSWERS-prior to bidding, owner undertakes a
process to design the project and all of its details to 100% complete plans and specs.
the owner is therefore responsible for success or failure of details of the design, and
warrants the sufficiency of design to the contractor. the owner is therefore liable to the
contractor for any gaps between plans and specifications and owner's requirements for
project performance

design details responsibility - CORRECT ANSWERS-the owner should define its
performance requirements and award the contract on the basis of preliminary design;
this makes the design-builder responsible for completing the design in accordance with
the owner's performance requirements. that also causes the design-builder to warrant

Geschreven voor

Instelling
DBIA TE
Vak
DBIA TE

Documentinformatie

Geüpload op
24 december 2024
Aantal pagina's
11
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$18.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
gideonngari
1.0
(1)

Maak kennis met de verkoper

Seller avatar
gideonngari Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
7
Lid sinds
1 jaar
Aantal volgers
0
Documenten
785
Laatst verkocht
2 weken geleden

1.0

1 beoordelingen

5
0
4
0
3
0
2
0
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen