A chart used for prioritizing time-critical events, deciding which events can occur
concurrently, and identifying slack time is the:
Decision matrix
PERT chart
Gantt chart
Organizational chart - Answers - PERT chart
Engineering design experience can be acquired through:
Testing prototypes
All of these answer choices
Completing successful projects
Observing results of design decisions
Studying failures - Answers - All of these answer choices
After using 3d printing software to add support structure and slice your model, you
output what to run the printer?
coordinate-code
g-code
3-code
layer-cod - Answers - g-code
Which of the following is NOT one of the 14 Grand Challenges for the 21st century as
identified by the National Academy of Engineering?
Provide access to clean water
Reverse-engineer the brain
Provide fiber-optic power transmission
Develop carbon sequestration - Answers - Provide fiber-optic power transmission
In the four-step "simple representation" of the engineering design cycle that we are
using in this class, what are the first two steps?
Group of answer choices - Answers - Problem Analysis and Design Generation
Engineers typically work in inter-dependent and multi-disciplinary teams.
True
False - Answers - True
A SWOT analysis is a structured way of identifying a potential design's Strengths,
Weaknesses, ______________, and Threats.
Offenses
Objectives
Opportunities
ANSWERS
A chart used for prioritizing time-critical events, deciding which events can occur
concurrently, and identifying slack time is the:
Decision matrix
PERT chart
Gantt chart
Organizational chart - Answers - PERT chart
Engineering design experience can be acquired through:
Testing prototypes
All of these answer choices
Completing successful projects
Observing results of design decisions
Studying failures - Answers - All of these answer choices
After using 3d printing software to add support structure and slice your model, you
output what to run the printer?
coordinate-code
g-code
3-code
layer-cod - Answers - g-code
Which of the following is NOT one of the 14 Grand Challenges for the 21st century as
identified by the National Academy of Engineering?
Provide access to clean water
Reverse-engineer the brain
Provide fiber-optic power transmission
Develop carbon sequestration - Answers - Provide fiber-optic power transmission
In the four-step "simple representation" of the engineering design cycle that we are
using in this class, what are the first two steps?
Group of answer choices - Answers - Problem Analysis and Design Generation
Engineers typically work in inter-dependent and multi-disciplinary teams.
True
False - Answers - True
A SWOT analysis is a structured way of identifying a potential design's Strengths,
Weaknesses, ______________, and Threats.
Offenses
Objectives
Opportunities