1 Code to follow when performing an internal inspection on pipe
Ans: API 510
570: 5.5.2
2 Positive Material Identification (PMI)
Ans: API 578
570: 5.12
3 Fitness for Service (FFS)
Ans: API 579
570: 7.7
4 Risked Based Inspection (RBI)
Ans: API 580
570: 5.2
5 Corrosion Under Insulation (CUI)
, [2]
Ans: API 583
570: 5.8
6 Valve Inspection & Testing
Ans: API 598
570: 5.13
7 Cathodic Protection
Ans: API 651
570: 9.6
8 Welding on In-Service Equipment containing Flammables
Ans: API 2201
570: 8.2.1
9 NDE Procedure Guidelines
Ans: ASME Sect V
31.3: 343
10 Design code for fabrication of piping relief devices
Ans: ASME Sect 8
31.3: 322.6.3.a
11 Welder & Weld Procedure Qualification
Ans: ASME Sect 9
31.3: 328.2
12 NDE Personnel Qualification
, [3]
Ans: ASNT SNT-TC-1A or CP-189
V: T-120.e
1 API 570 Scope (Alteration, Inspection, Repair, Rerate)
Ans: AIRR
570: 1.1.1
2 API 570 AI's Employer (Jurisdiction, User, Insurance company, Contractor)
Ans: JUIC
570: 3.1.6
3 API 570 Repair Organization (authorized by Jurisdiction, Owner, Contractor)
Ans: JOC
570: 3.1.89
4 Primary responsibilities of API 570 AI (Testing, Inspection, Examination)
Ans: A TIE
570: 4.3.4
5 Determine Corrosion Rate for New Service or Change in Service (Same or Similar Service,
Owner's Experience, Published Data, or Inspect in 3 months)
Ans: SOPI
570: 7.3
1 Define - Alteration
Ans: Physical Change
570: 3.1.3
, [4]
2 Define - Repair
Ans: Restore - Suitable
570: 3.1.88
3 Corrosion - Cause for fatigue crack
Ans: Cyclic Stress
570: 3.1.18
574: 7.4.11
4 Define - Imperfection that exceeds the acceptance criteria
Ans: Defect
570: 3.1.22
5 Define - Discontinuity that may or may not exceed the acceptance criteria
Ans: Imperfection
570: 3.1.35
6 Define - RBI's two Primary Factors
Ans: Probability & Consequence
570: 5.2.1
7 RBI - Two Primary Factors of Consequence of Failure
Ans: Process Fluid & Volume
570: 5.2.3
8 Repairs - # of new flange assemblies to be inspected during repairs and alterations