Well construction is comprised of the following componets? - Answer✔drilling, installation of
casing, placing well screens, grouting, DEVELOPMENT
Minimum grouting distance? - Answer✔10' is code
Artesian Well - Answer✔Artesian pressure is the result of gravity and the confining Aquifer
Artesian Well Layers - Answer✔CONFINING Layer (top)
CONFINED AQUIFER (middle)
IMPERMEABLE Layer (bottom)
Types of drilling techniques - Answer✔Cable tool, Air rotary, Mud rotary, Reverse circulation
rotary, Jetting & Driving
GROUTING - Answer✔IS THE ACT OF INJECTING CERTAIN SUBSTANCES INTO VOID SPACE TO
REDUCE OR ELIMINATE THEIR PERMEABILITY, CONSOLIDATE OR INCREASE THEIR STRENGTH.
(Filling space between the casing and bore hole with cement or clay)
Methods of Grouting include - Answer✔Tremie pipe outside casing,
Tremie pipe inside casing,
Casing method or Halliburton method
Neat Cement Ratio - Answer✔Cement and Water, 5.5 to 6gal of h20 to 1 cubic foot of Portland
cement with 3% bentonite to prevent shrinkage
Tremie Pipe Outside Casing - Answer✔Grout placed through small pipe outside casing,
Centering guides are placed along length of casing,
Lower end of casing has drillable plug,