Who is responsible for managing the progress of work during a Sprint?
The Development Team
Who is on the Scrum Team?
1) The Scrum Master
2) The Product Owner
3) The Development Team
Which two things does the Development Team do during the first Sprint?
1) Deliver an increment of potentially releasable software
2) Develop and deliver at least one piece of functionality
Which of the below are roles on a Scrum Team?
1) Development Team
2) Product Owner
3) Scrum Master
Which statement best describes the Sprint Review?
It is when the Scrum Team and stakeholders inspect the outcome of the Sprint and figure out what to do
next (upcoming Sprint) To inspect the product increment with stakeholders and collect feedback on next
steps
The time-box for a Daily Scrum is?
15 minutes
When might a Sprint be abnormally cancelled?
When the Sprint Goal becomes obsolete
What is the role of Management in Scrum?
Support the Product Owner with insights and information into high value product and system
capabilities. Support the Scrum Master to cause organizational change that fosters empiricism, self-
organization,
The three pillars of empirical process control are:
Inspection, Transparency, Adaptation
What is the recommended size for a Development Team (within the Scrum Team)?
3 to 9
, Who should know the most about the progress toward a business objective or a release, and be able
to explain the alternatives most clearly?
The Product Owner
When does a Development Team member become the sole owner of a Sprint Backlog item?
Never. All Sprint Backlog items are "owned" by the entire Development Team, even though each one
may be implemented by an individual development team member
Scrum does not have a role called "project manager"
True
Which statement best describes Scrum?
A framework within which complex products in complex environments are developed. A framework
within which people can address complex adaptive problems, while delivering valuable products.
When does the next Sprint begin?
Immediately after the conclusion of the previous Sprint.
The length of a Sprint should be:
ALL of these answers are correct.
1) Short enough to keep the business risk acceptable to the Product Owner
2) Short enough to be able to synchronize the development work with other business events
3) No more than one month.
When is a Sprint over?
When the time-box expires.
Who is required to attend the Daily Scrum?
The Development Team
The Product Backlog is ordered by:
Whatever is deemed most appropriate by the Product Owner.
The purpose of a Sprint is to produce a done increment of working product
True
Who has the final say on the order of the Product Backlog?
The Product Owner
What is the main reason for the Scrum Master to be at the Daily Scrum?
He or she does not have to be there; he or she only has to ensure the Development Team has a Daily
Scrum