BREAKDOWN
What is a fundamental
element of a contract?
mutual acceptance
Which of the following contract types is
generally considered to have the most risk
for the contractor?
lump sum
What contract type is best
used if the scope is well defined but not the
quantities of material?
. unit price
In which delivery method is the construction
administrator most like a consultant?
CM agency
. Which statement is true about the design-build
delivery method from the owner's
perspective?
There is a single source of fault for
building system failures.
Which delivery method has the most risk for
the contractor?
design-build
Which of the following is a major difference
between a CM agency and a CM at risk?
caps the construction costs the owner is
required to pay
. Under which legal structure are the least
total taxes paid for the goods and services
provided by the company?
sole proprietorship
Total float (TF)
, how much an activity can be
delayed before the critical path is delayed.
Free float (FF)
how much an activity can be
delayed before it delays the subsequent
activity.
Total Float =
Late Start - Early Start
Free Float =
Early Start (next activity) - Early Finish
What classification of activity would "shop
drawing rejection" be?
procurement
What classification of activity would
"building programming" be?
design
What defines the term trade
stacking?
the loss of productivity by placing too
many workers in too small a space
A Gantt chart is which type of scheduling
tool?
bar chart
Tieback bracing system
an external
bracing system that uses metal rods or wires
anchored into rock or soil outside of an excavation
to support the face of an excavation.
Sheet Pilings
designed to stabilize
the sides of open excavations by resisting the
lateral pressure of soil and water.
Cofferdams