Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

AIC 301 EXAM: LATEST A+ QUESTIONS AND ANSWERS BREAKDOWN

Beoordeling
-
Verkocht
-
Pagina's
14
Cijfer
A+
Geüpload op
22-02-2025
Geschreven in
2024/2025

AIC 301 EXAM: LATEST A+ QUESTIONS AND ANSWERS BREAKDOWN What is a fundamental element of a contract? mutual acceptance Which of the following contract types is generally considered to have the most risk for the contractor? lump sum What contract type is best used if the scope is well defined but not the quantities of material? . unit price In which delivery method is the construction administrator most like a consultant? CM agency . Which statement is true about the design-build delivery method from the owner's perspective? There is a single source of fault for building system failures. Which delivery method has the most risk for the contractor? design-build Which of the following is a major difference between a CM agency and a CM at risk? caps the construction costs the owner is required to pay . Under which legal structure are the least total taxes paid for the goods and services provided by the company? sole proprietorship Total float (TF) how much an activity can be delayed before the critical path is delayed. Free float (FF) how much an activity can be delayed before it delays the subsequent activity. Total Float = Late Start - Early Start Free Float = Early Start (next activity) - Early Finish What classification of activity would "shop drawing rejection" be? procurement What classification of activity would "building programming" be? design What defines the term trade stacking? the loss of productivity by placing too many workers in too small a space A Gantt chart is which type of scheduling tool? bar chart Tieback bracing system an external bracing system that uses metal rods or wires anchored into rock or soil outside of an excavation to support the face of an excavation. Sheet Pilings designed to stabilize the sides of open excavations by resisting the lateral pressure of soil and water. Cofferdams temporary enclosures primarily used to hold back water for activities requiring a dry work area. Pile Jetting uses pipes to deliver concentrated jets of water or air to loosen the soil directly beneath the piling scraper a multipurpose piece of equipment designed to excavate, load, haul, and discharge soil dragline excavates material by using a (cable) to pull a bucket toward the crane. clamshell a bucket is a hinged bucket used to vertically excavate material. T Stationary cranes erected and fixed to a single location on the job site. Tower cranes often erected and disassembled in sections by mobile cranes Mobile cranes are capable of moving from one place to another without being disassembled Two of the most common types of mobile cranes used in construction crawler cranes and vehicle-mounted cranes crawler cranes

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

AIC 301 EXAM: LATEST A+ QUESTIONS AND ANSWERS
BREAKDOWN
What is a fundamental
element of a contract?

mutual acceptance

Which of the following contract types is
generally considered to have the most risk
for the contractor?

lump sum

What contract type is best
used if the scope is well defined but not the
quantities of material?

. unit price

In which delivery method is the construction
administrator most like a consultant?

CM agency

. Which statement is true about the design-build
delivery method from the owner's
perspective?

There is a single source of fault for
building system failures.

Which delivery method has the most risk for
the contractor?

design-build

Which of the following is a major difference
between a CM agency and a CM at risk?

caps the construction costs the owner is
required to pay

. Under which legal structure are the least
total taxes paid for the goods and services
provided by the company?

sole proprietorship

Total float (TF)

, how much an activity can be
delayed before the critical path is delayed.

Free float (FF)

how much an activity can be
delayed before it delays the subsequent
activity.

Total Float =

Late Start - Early Start

Free Float =

Early Start (next activity) - Early Finish

What classification of activity would "shop
drawing rejection" be?

procurement

What classification of activity would
"building programming" be?

design

What defines the term trade
stacking?

the loss of productivity by placing too
many workers in too small a space

A Gantt chart is which type of scheduling
tool?

bar chart

Tieback bracing system

an external
bracing system that uses metal rods or wires
anchored into rock or soil outside of an excavation
to support the face of an excavation.

Sheet Pilings

designed to stabilize
the sides of open excavations by resisting the
lateral pressure of soil and water.

Cofferdams

Geschreven voor

Vak

Documentinformatie

Geüpload op
22 februari 2025
Aantal pagina's
14
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$12.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TopGradeSolutions Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
95
Lid sinds
2 jaar
Aantal volgers
9
Documenten
13297
Laatst verkocht
5 dagen geleden
TOPGRADESOLUTIONS

Here we offer revised study materials to elevate your educational outcomes. We have verified learning materials (Research, Exams Questions and answers, Assignments, notes etc) for different courses guaranteed to boost your academic results. We are dedicated to offering you the best services and you are encouraged to inquire further assistance from our end if need be. Having a wide knowledge in Nursing, trust us to take care of your Academic materials and your remaining duty will just be to Excel. Remember to give us a review, it is key for us to understand our clients satisfaction. We highly appreciate clients who always come back for more of the study content we offer, you are extremely valued. All the best.

Lees meer Lees minder
4.9

171 beoordelingen

5
159
4
7
3
4
2
0
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen