Estimating Final Exam FDOT Final Estimates EXAM PREP QUESTIONS WITH CORRECT ANSWERS We put together estimates all the time in our everyday lives, often with little or no calculating. - CORRECT ANSWERTrue The different project delivery systems use the same types of estimates— conceptual, preliminary and detailed—at various stages in the development of the project. - CORRECT ANSWERFalse

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

Estimating Final Exam FDOT Final
Estimates EXAM PREP QUESTIONS
WITH CORRECT ANSWERS
We put together estimates all the time in our everyday lives, often with little or no calculating. -
CORRECT ANSWER✅✅✅True


The different project delivery systems use the same types of estimates— conceptual, preliminary
and detailed—at various stages in the development of the project. - CORRECT
ANSWER✅✅✅False


With the design- build method, the owner indicates that he or she requires a certain facility and
usually outlines some parameters relating to location, size, design and the desired time of
occupancy. - CORRECT ANSWER✅✅✅True


Most general contractors and subtrades enter into cost-plus contracts in order to perform a
defined scope of work. - CORRECT ANSWER✅✅✅False


A(n) ____ in its essence is an assessment of the probable total cost of some future activity. -
CORRECT ANSWER✅✅✅estimate


A ____ estimate has to be prepared from a minimum amount of information because it is
required at a time when the project is often little more than a vague idea in the mind of the
owner. - CORRECT ANSWER✅✅✅conceptual


Once the design of a project is underway, budget amounts can be established for the various
elements of the project using procedures for a ____ estimate. - CORRECT
ANSWER✅✅✅preliminary

,Using a construction management organization seeks to facilitate overlap between project stages,
often referred to as ____, to allow earlier completion of the project. - CORRECT
ANSWER✅✅✅fast tracking


____ contracts are usually the owner's choice of last resort because they can place the owner in a
vulnerable financial position. - CORRECT ANSWER✅✅✅Cost-plus


____ contracts are based on a pricing schedule that consists of a breakdown of the work and
estimated quantities for each of the items on the breakdown. - CORRECT
ANSWER✅✅✅Unit-price


The basis of a ____ is the accurate assessment of the work in the form of a quantity takeoff that
can only be obtained from the full design of the project - CORRECT
ANSWER✅✅✅detailed estimate


Construction groups in major cities have formed associations or plan service centers where both
public and private bodies may deposit plans and specifications of projects calling for bids. -
CORRECT ANSWER✅✅✅True


In a closed bid system the number of companies invited to bid is typically limited to no more
than ten contractors who are known to the owner or designers and who meet the qualification
criteria set by the owner. - CORRECT ANSWER✅✅✅False


An effective way to proceed with the planning of estimating operations is achieved by means of
a simple line chart form of time schedule. - CORRECT ANSWER✅✅✅False


On most projects general contractors request two complete sets of bid documents for estimating a
project. - CORRECT ANSWER✅✅✅True


If an estimator does not know exactly what the computer is accomplishing in the preparation of
an estimate, the estimator will not be in control of the process. - CORRECT
ANSWER✅✅✅True

, The use of fax machines, cellular telephones, and e-mail has had little impact on the bidding
process as it is still mostly a manual process. - CORRECT ANSWER✅✅✅False


Agencies of the U.S. government use a standard form called the "____" to provide bid
information. - CORRECT ANSWER✅✅✅Pre-Solicitation Notice


Private owners often directly invite contractors to bid on their construction projects in a system
known as a(n) ____ system. - CORRECT ANSWER✅✅✅Closed bid


A method of addressing the problem of bids from contractors of questionable financial situation
and experience capability is to call for bids only from ____ contractors. - CORRECT
ANSWER✅✅✅prequalified


Designers usually require a cash or certified check deposit from contractors who obtain bid
documents and the deposit is reimbursed when the drawings and specifications are returned to
the designer's office in "____." - CORRECT ANSWER✅✅✅Good order


A method of handling the problem of review questions is to compile a list of all the questions
that arise, the ____, then later make a single call to the designer to cover all the items that have
accumulated. - CORRECT ANSWER✅✅✅query list


Significant details provided in response to questions about a bid will be incorporated into written
documents that are distributed to all bidders in publications that are known as ____. - CORRECT
ANSWER✅✅✅addenda


Perhaps the most important item considered at the estimate review is ____. - CORRECT
ANSWER✅✅✅the amount of fee to include in the bid price


While an experienced estimator will certainly know what to look for and assess when
investigating the site, the presence of the ____ or a project superintendent on the visit will
always be valuable if only to offer alternative viewpoints in the evaluation of the data obtained. -
CORRECT ANSWER✅✅✅chief estimator

Geschreven voor

Vak

Documentinformatie

Geüpload op
24 februari 2025
Aantal pagina's
21
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$10.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
StudyAceHub

Maak kennis met de verkoper

Seller avatar
StudyAceHub Abacus College, Oxford
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1
Lid sinds
1 jaar
Aantal volgers
0
Documenten
846
Laatst verkocht
6 maanden geleden
Comprehensive Study Guides materials and simplified exam prep Q and A .

Clear ,well-structured study materials made with care to support your learning journey.

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen