2025 Actual Exam With Correct Verified
Answers | Guaranteed A+ Exam
An activity normally has an expected... - ✔✔✔ Correct Answer >
Duration, Cost, & Resource requirment
During what phase does the close interaction between Project
Management and Procurement influence the success of a project? -
✔✔✔ Correct Answer > Bid Preparation
A change order and claim strategy should be prepared at which
milestone? - ✔✔✔ Correct Answer > @ PM040 - Bid Approval
The order intake calc must be determined no less thatn "X" weeks after
the contract becomes effective? - ✔✔✔ Correct Answer > 4 weeks
,Project Manager (Target) Agreement - ✔✔✔ Correct Answer >
Documents mutually agreed upon (w/ Business Mgr.) results
expected, plus responsibilities, authorizations, and resources
available to PM.
- Completed & Signed @ PM100, no later than PM200
- Valid until PM650
- Includes project description, financial/strategic/quality targets,
milestones, LL, responsibilities of PM, etc.
Letter of Empowerment - ✔✔✔ Correct Answer > Informs organization
(and stakeholders) of the responsibility & authority of the person
responsible for a project in the sales &/or execution phase. Is proper
communication, input is before handover (PM080)
Contains:
- project designation & period of validity
- assignment of relevant authorities & obligations
- overview of responsibilities
,- reference to the valid PM method in accordance w/ PM@Siemens
Independent Project Organization - ✔✔✔ Correct Answer > Project
leader has entire responsibility for project & authority over team
members. Decisions can be made quickly.
Matrix Organization - ✔✔✔ Correct Answer > PM shares responsibility
w/ functional managers for assigning priorities & directing the work of
individuals assigned. Individual remains assigned to the functional
manager, but works with the PM.
Who must be considered w/ every project adjustment? - ✔✔✔ Correct
Answer > Relevant stakeholders
Main aspects to consider for project strategy & implementation? -
✔✔✔ Correct Answer > - Stringent across project
- Communicated w/ team, & stakeholders
- Alignment w/ business strategy
, How can I ensure contribution of project team members to the
implementation of the business strategy for my project? - ✔✔✔
Correct Answer > - Communicate tailored strategy to project team
- Use strategy as basis for identifying opportunities
- Use info from won/loss bids to improve strategy for future bids
PACT - Project Acceleration by Coaching & Teamwork - ✔✔✔ Correct
Answer > - Mandatory for bid phase, project opening/clarification, not
LL.
- Workshop brings together everyone to understand topics of project,
brings team up to speed, enables coaching & teamwork among
members
Siemens Values - ✔✔✔ Correct Answer > Integrity, impartiality,
honesty, fairness, truthfullness.
Core Team - ✔✔✔ Correct Answer > PM, CPM, TPM, QMiP, Claim
Mgr., Risk Mgr., etc.