CQM-C EXAM QUESTIONS AND ANSWERS
GRADED A+
The purpose of Construction Quality Management is to: - Answer - Achieve the quality
established by properly developed requirements through the combined responsibility,
but seperate efforts of contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ensure that
construction is performed. - Answer - According to plans and specifications, on time,
within a defined budget and a safe work environment.
Partnering relationships are based upon: - Answer - Building trust and dedication to
common goals
It is the responsibility of Quality Assurance Personnel to: - Answer - Periodically verify
that the contractors system of control is working effectively.
An effective contractor quality control program will: - Answer - Be an incentive for work
to be done correctly the first time resulting in earlier completion, reduced field overhead
costs, and greater profits.
The success or failure of all contractors is based upon: - Answer - The ability to control
costs, finance work, estimate jobs, schedule the work, and maintain effective quality
control.
Quality Assurance Personnel have the responsibility to: - Answer - Require contractors
to maintain the quality specified in the plans and specifications.
Inspection is: - Answer - The process by which ongoing and completed work is
examined
, During the punch-out inspection of a project: - Answer - Quality Assurance Personnel
must assure that the contractor prepares a punch-list and makes corrections.
If there is a disagreement whether the contractors work complies with the contract: -
Answer - The government makes the final determination
Characteristics that describe a definable feature of work include: - Answer - Cross-
referenced listings to the contractors construction schedule that may have more than
one definable feature under a section of the specifications.
The _____________________ consists of daily checks of the work to assure continuing
compliance with contract requirements. - Answer - Follow-up phase
The Quality Assurance Plan: - Answer - Is a government management tool establishing
staffing, training, pre-award activities, and surveillance activities.
Testing is extremely important in construction quality management and is performed by:
- Answer - Both the contractor and the government
If the contractor does not provide an adequate superintendent, the contract allows the
contracting officer to: - Answer - Require the contractor to assume personal supervision
of the work.
The Quality Control Plan: - Answer - Is the foundation upon which quality work is based
and outlines planned quality control procedures.
Tests that are unannounced, randomly performed, and repeat quality control tests are: -
Answer - Quality Assurance tests
If initial review of the quality control plan shows it to be unacceptable: - Answer - The
contractor makes changes before acceptance.
GRADED A+
The purpose of Construction Quality Management is to: - Answer - Achieve the quality
established by properly developed requirements through the combined responsibility,
but seperate efforts of contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ensure that
construction is performed. - Answer - According to plans and specifications, on time,
within a defined budget and a safe work environment.
Partnering relationships are based upon: - Answer - Building trust and dedication to
common goals
It is the responsibility of Quality Assurance Personnel to: - Answer - Periodically verify
that the contractors system of control is working effectively.
An effective contractor quality control program will: - Answer - Be an incentive for work
to be done correctly the first time resulting in earlier completion, reduced field overhead
costs, and greater profits.
The success or failure of all contractors is based upon: - Answer - The ability to control
costs, finance work, estimate jobs, schedule the work, and maintain effective quality
control.
Quality Assurance Personnel have the responsibility to: - Answer - Require contractors
to maintain the quality specified in the plans and specifications.
Inspection is: - Answer - The process by which ongoing and completed work is
examined
, During the punch-out inspection of a project: - Answer - Quality Assurance Personnel
must assure that the contractor prepares a punch-list and makes corrections.
If there is a disagreement whether the contractors work complies with the contract: -
Answer - The government makes the final determination
Characteristics that describe a definable feature of work include: - Answer - Cross-
referenced listings to the contractors construction schedule that may have more than
one definable feature under a section of the specifications.
The _____________________ consists of daily checks of the work to assure continuing
compliance with contract requirements. - Answer - Follow-up phase
The Quality Assurance Plan: - Answer - Is a government management tool establishing
staffing, training, pre-award activities, and surveillance activities.
Testing is extremely important in construction quality management and is performed by:
- Answer - Both the contractor and the government
If the contractor does not provide an adequate superintendent, the contract allows the
contracting officer to: - Answer - Require the contractor to assume personal supervision
of the work.
The Quality Control Plan: - Answer - Is the foundation upon which quality work is based
and outlines planned quality control procedures.
Tests that are unannounced, randomly performed, and repeat quality control tests are: -
Answer - Quality Assurance tests
If initial review of the quality control plan shows it to be unacceptable: - Answer - The
contractor makes changes before acceptance.