Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CDS - EXAM 1 QUESTIONS AND ANSWERS

Beoordeling
-
Verkocht
-
Pagina's
9
Cijfer
A+
Geüpload op
05-03-2025
Geschreven in
2024/2025

CDS - EXAM 1 QUESTIONS AND ANSWERS

Instelling
Vak

Voorbeeld van de inhoud

CDS - EXAM 1 QUESTIONS AND ANSWERS
Labor and material payment bonds provide the necessary protection on public projects -
Correct Answer- TRUE

Miller act corresponds with what.? - Correct Answer- Labor and material payment bond

Architects should not advise owners and the legal sufficiency of required affidavits,
waivers, or releases of liens. - Correct Answer- TRUE

Liens are not permitted on public projects. - Correct Answer- TRUE

Architect must review, approve, and promptly submit shop drawings required by the
contract documents. - Correct Answer- TRUE

An architect approved shop drawings which deviated from the contract documents. -
Correct Answer- Changes in contract drawings must be submitted in writing to architect
before becoming affective, not equal to revisions within shop drawings.

Who is responsible for errors and omissions in shop drawings? - Correct Answer-
General Contractor

Revisions not requested by the architect on resubmitted shop drawings don't require
architect's approval? - Correct Answer- FALSE

A contractors stamp of approval on shop drawings means that the contractor has
already determined all criteria related thereto. - Correct Answer- FALSE

AIA document B101 is used to outline the architects service obligations? - Correct
Answer- TRUE

The architects responsibilities are re-stated within the AIA General Conditions Doc
A201. - Correct Answer- TRUE

Contractors may not know what services the architect is obligated to perform if what
document is not part of the contract documents. - Correct Answer- AIA Document B101

In review of shop drawings the general conditions Document A201 clearly states? -
Correct Answer- Matters outside the scope of the design concept and the contract
documents are not reviewed.

, If an architect had performed their services using stipulations of AIA documents A201 &
B141 within a ______ there should be no concern about professional liability. But
general liability is different. - Correct Answer- Standard of care

Calendar days - Correct Answer- 7 / Week

Liquidated damages is a provision included in the? - Correct Answer- Owner-contractor
agreement. Document A101.

An amount of money stipulated in the contract that is chargeable against the contractor
is reimbursement for damages suffered by the owner because the contractors failure to
fulfill his or her contractual obligation's. - Correct Answer- Liquidated damages

What clause should be used when a slight delay in schedule can cause a breach of
contract? - Correct Answer- Time is of the essence

CPM is superior to a Bar Chart because it shows durations, sequences and
relationships to other activities. - Correct Answer- TRUE

And small projects what type of progress schedule should be used? - Correct Answer-
Bar chart

And larger complex projects what type of progress schedule should be used? - Correct
Answer- Critical path method CPM

How many days the contractor have to notify the architect in conditions of force
majeure? - Correct Answer- 21 days

Time extensions caused by the owner automatically entitle the contractor to monetary
damages? - Correct Answer- FALSE

Standard AIA documents provided means by which the contractor may make a claim for
time extensions, monetary damages, or both. - Correct Answer- TRUE

General requirements are often used to detail provisions related to scheduling and the
consequences of delays. - Correct Answer- FALSE

What is required prior to the contractor submitting the first application for payment? -
Correct Answer- Schedule of values

Geschreven voor

Vak

Documentinformatie

Geüpload op
5 maart 2025
Aantal pagina's
9
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$32.58
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
NurseJoanne

Maak kennis met de verkoper

Seller avatar
NurseJoanne NURSING, ECONOMICS, MATHEMATICS, BIOLOGY, AND HISTORY MATERIALS BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS, AND STUDY GUIDE MATERIALS WITH GUARANTEED A+ I am a dedicated medical practitioner with diverse knowledge in matters
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
4
Lid sinds
1 jaar
Aantal volgers
0
Documenten
10
Laatst verkocht
8 maanden geleden
Nightbirde002

Best Educational Resources for Students.

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen