1. Untilbtheb1980s,bprojectbmanagementbprimarilybfocusedbonbprovidingbschedulebandbresourcebdatabtobtopbmanagementbinbt
hebmilitary,bcomputer,bandbconstructionbindustries.
a. True
b. False
ANSWER: True
RATIONALE:
Feedback:bUntilbtheb1980s,bprojectbmanagementbprimarilybfocusedbonbprovidingbscheduleba
ndbresourcebdatabtobtopbmanagementbinbthebmilitary,bcomputer,bandbconstructionbindustries.
Today’sbprojectbmanagementbinvolvesbmuchbmore,bandbpeoplebinbeverybindustrybandbeverybco
untrybmanagebprojects.
POINTS: 1
DIFFICULTY: Difficulty:bEasy
REFERENCES: p.2
LEARNINGbOBJECTIVES:b INFO.SCHW.14.1b-bLO:b1-1
NATIONALbSTANDARDS:b UnitedbStatesb-bBUSPROG:bTechnology
TOPICS: Introduction
KEYWORDS: Bloom's:bKnowledge
2. Abdifferencebbetweenboperationsbandbprojectsbisbthatboperationsbendbwhenbtheirbobjectivesbhavebbeenbreached,bwhereasb
projectsbdobnot.
a. True
b. False
ANSWER: False
RATIONALE:
Feedback:bProjectsbarebdifferentbfromboperationsbinbthatbtheybendbwhenbtheirbobjectivesbha
vebbeenbreachedborbthebprojectbhasbbeenbterminated.
POINTS: 1
DIFFICULTY: Difficulty:bModerate
REFERENCES: p.4
LEARNINGbOBJECTIVES:b INFO.SCHW.14.2b-bLO:b1-2
NATIONALbSTANDARDS:b UnitedbStatesb-bBUSPROG:bAnalytic
TOPICS: WhatbisbabProject?
KEYWORDS: Bloom's:bComprehension
3. Everybprojectbshouldbhavebabwell-definedbobjective.
a. True
b. False
ANSWER: True
RATIONALE: Feedback:bAbprojectbhasbabuniquebpurpose.bEverybprojectbshouldbhavebabwell-
definedbobjective.
POINTS: 1
DIFFICULTY: Difficulty:bEasy
REFERENCES: p.6
LEARNINGbOBJECTIVES:b INFO.SCHW.14.2b-bLO:b1-2
NATIONALbSTANDARDS:b UnitedbStatesb-bBUSPROG:bAnalytic
Cengage Learning Testing, Powered by Cognero Page 1
,Chapter 1: Introduction to Project Management
TOPICS: WhatbisbabProject?
Cengage Learning Testing, Powered by Cognero Page 2
, Chapter 1: Introduction to Project Management
KEYWORDS: Bloom's:bKnowledge
4. Projectsbshouldbbebdevelopedbinbincrements.
a. True
b. False
ANSWER: True
RATIONALE:
Feedback:bAbprojectbisbdevelopedbusingbprogressivebelaboration.bProjectsbareboftenbdefin
edbbroadlybwhenbtheybbegin,bandbasbtimebpasses,bthebspecificbdetailsbofbthebprojectbbecome
bclearer.bTherefore,bprojectsbshouldbbebdevelopedbinbincrements.
POINTS: 1
DIFFICULTY: Difficulty:bModerate
REFERENCES: p.6
LEARNINGbOBJECTIVES:b INFO.SCHW.14.2b-bLO:b1-2
NATIONALbSTANDARDS:b UnitedbStatesb-bBUSPROG:bAnalytic
TOPICS: WhatbisbabProject?
KEYWORDS: Bloom's:bComprehension
5. Resourcesbinbabprojectbshouldbbebusedbeffectivelybbecausebtheybareblimited.
a. True
b. False
ANSWER: True
RATIONALE:
Feedback:bAbprojectbrequiresbresources,boftenbfrombvariousbareas.bResources,bhowever,ba
reblimitedbandbmustbbebusedbeffectivelybtobmeetbprojectbandbotherbcorporatebgoals.
POINTS: 1
DIFFICULTY: Difficulty:bModerate
REFERENCES: p.b7
LEARNINGbOBJECTIVES:b INFO.SCHW.14.2b-bLO:b1-2
NATIONALbSTANDARDS:b UnitedbStatesb-bBUSPROG:bAnalytic
TOPICS: WhatbisbabProject?
KEYWORDS: Bloom's:bComprehension
6. Abprojectbmanager’sbprimarybrolebisbtobprovidebthebfundingbforbabproject.
a. True
b. False
ANSWER: False
RATIONALE: Feedback:bAbprojectbsponsorbusuallybprovidesbthebdirectionbandbfundingbforbabproject.
POINTS: 1
DIFFICULTY: Difficulty:bEasy
REFERENCES: p.7
LEARNINGbOBJECTIVES:b INFO.SCHW.14.2b-bLO:b1-2
NATIONALbSTANDARDS:b UnitedbStatesb-bBUSPROG:bAnalytic
TOPICS: WhatbisbabProject?
KEYWORDS: Bloom's:bKnowledge
Cengage Learning Testing, Powered by Cognero Page 3