What are the 3 basic types of documents used in construction contracts
a. Bidding and Contract Requirements
b. Drawings
c. Specifications
Which of the following are included in the Bidding Documents but not in the
Construction Contract Documents
a. Instructions to Bidders
b. Bid Form
T or F? Specs describe the construction in text form.
True
T or F? Construction specs apply on to the Construction phase of a project.
False
T or F? Development of construction specs for a project begins during the Contract
Document phase.
False
T or F? Procurement docs include construction specs
True
T or F? Design-Bid-Build and Design-Build are two valid methods to procure a
construction project.
True
T or F? Contract Documents are identified in the Agreement for a construction project.
True
T or F? Drawings are the graphic descriptions of the work to be performed by the
Contractor.
True
The Agreement includes which of the following for the construction contract.
a. Summary of the work to be performed by the Contractor
b. Time within which work shall be completed
c. Amount of money to be paid by Owner to Contractor
d. All of the above
, T or F? The purpose of the Drawings and the Specs is to communicate information
between the A/E and the Contractor
True
T or F? The term work is defined in the General Conditions of the Contract
True
The Contract Drawings designate which of the following relationships between elements
of a facility:
a. Identification of Equipment
b. Limits of areas where work is performed
c. Dimensions and sizes of components in the construction
d. All of the above
T or F? Drawings indicate which elements of the work shall be performed by specific
subcontractors.
False
T or F? Drawings are organized according to the design discipline responsible for their
preparation.
True
Drawings should not indicate which of the following?
a. Work performed by the owner
b. Proprietary names for products indicated
c. Alternate bid conditions
d. Locations for each factory-manufactured component
Specs should not indicate which of the following?
a. Descriptions for product bid conditions
b. Requirements for installation of equipment
c. Dimensional requirements for locating equipment
d. Quality requirements for field installation and finishing
T or F? Repeating requirements on the Drawings and in the Specs ensures proper
installation of materials.
False
Parties who rely upon specs for bidding and construction include all but which of the
following?