for Initial Response, ICS-200 Final Exam
Questions and Answers
Which Incident Type is limited to one operational period, does not
require a written Incident Action Plan, involves Command and
General Staff only if needed, and requires several single resources?
A. Type 3
B. Type 5
C. Type 2 D.
Type 4 -
correct answer ✅D. Type 4
When the supervisor-to-subordinate ratio exceeds manageable
span of control, additional Teams, Divisions, Groups, Branches, or
Sections can be established. Which NIMS Management
characteristic does this describe? A. Modular Organization B.
Management by Objectives C. Comprehensive Resource
Management D. Formal Communication -
correct answer ✅A. Modular Organization
When command is transferred, then all personnel involved in the
incident should be told: A. The limits of the Incident Commander's
scope of authority B. The Incident Commander's cell phone number
C. The qualifications of the incoming Incident Commander D. The
effective time and date of the transfer -
correct answer ✅D. The effective time and date of the transfer
, IS-200.C: Basic Incident Command System
for Initial Response, ICS-200 Final Exam
Questions and Answers
Which of these is NOT a tool that you would need at the incident?
A. Agency Procedures Manual B. Exercise Plan C. Emergency
Operations Plan (EOP) D. Maps of the affected area -
correct answer ✅B. Exercise Plan
Which type of briefing is delivered to individual resources or crews
who are assigned to operational tasks and/or work at or near the
incident site? A. Staff-level briefing B. Operational Period Briefing C.
Field-level briefing D. Section-level briefing -
correct answer ✅C. Field-level briefing
An Incident Commander's scope of authority is derived from
existing laws, agency policies, and/or ______. A. Outgoing Incident
Commander B. IMT Position Description C. Delegation of Authority
D. Incident Action Plan -
correct answer ✅C. Delegation of Authority
Which statement best describes ICS Form 201? A. It allows a Single
Resource Unit Leader to track major activities during each
operational period. B. Lists all resources and organization
assignments for the upcoming operations period C. It is completed