A contractor does not notify a change of address and so does not receive a timely Notice of
Renewal. Who is responsible for when the contractor does not renew his license on time? -
Answer- The Licensee Contractor
A Designated Employee should be? - Answer- At least 18, Full Time, Passed Required Exams
What is the initial Recovery Fund fee? - Answer- $25.00
If a contractor ears more that $_______ per year, then the contractor is required to have a Class
A. - Answer- $750,000.00
If a contract awards more than $_________ per payment, the contractor is required to have a
Class A. - Answer- $120,000.00
An Erosion control conservation plan needs to be approved within ____ days. - Answer- 45
Where do you go to file an appeal of a violation to the USBC provisions? - Answer- To The BBCA
A contractor is required to submit a renewal within____ days of the expiration date? - Answer- 30
Who can file a complaint against a contractor? - Answer- any one
What is required when changing the from of entity from a sole proprietorship to a corporation -
Answer- A new license
What is the maximum fund allowed for a single contractor? - Answer- $40,000.00
To Whom should the stop work order be given? - Answer- Owner, Owner's Agent, Contractor
Within how many days should be submitted an appeal for construction? - Answer- 90 Days
An appeal of the local building officials decision to refuse to grant a modification to the USBC
MUST be made within how many days? - Answer- 90 Days
Documents related to a contract should be kept for ______ years? - Answer- 5 Years
Where should one set of all approved building documents be kept? - Answer- At the building site
An erosion control conservation specification needs to be approved within_____ days - Answer-
60 days
After notification by the code official, an application for a permit shall be considered to have been
abandoned for _____ months - Answer- 6
Where is the Recovery Fund used? - Answer- to pay claimants subject to improper or dishonest
conduct