Gantt Chart
The project will have a duration of 12 months.
Activities Months Expected Output
Persons
Initialization Activities: 1 2 3 4 5 6 7 8 9 10 11 12 Set of goals to guide
Conceptualize a set of goals the project
(Setting and Framing goals)
x
Visualization: Number of problem
Conducting a problem x x report
analysis(Identifying the
problems)
Planning and Outlining: List of total number of
Assessments of Needs x x needs (sports
(Total number of equipment)
equipment’s)
Realization: Budgetary report
Purchasing the equipment’s x
Distribution: Narrative report
Turnover Ceremony x (Documentations)
Utilization Performance report
x x x x x x
Monitoring: Monitoring sheets
Continuous monitoring x x x x x x
Evaluation: Evaluation sheets
Feed backing and improving x