Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

DBIA EXAM ACTUAL QUESTIONS AND ANSWERS WITH COMPLETE SOLUTIONS VERIFIED GRADED A++

Beoordeling
-
Verkocht
-
Pagina's
9
Cijfer
A+
Geüpload op
31-03-2025
Geschreven in
2024/2025

DBIA EXAM ACTUAL QUESTIONS AND ANSWERS WITH COMPLETE SOLUTIONS VERIFIED GRADED A++ Terms in this set (175) DBIA Document 580 - Teaming Agreement Between Design-Builder and teaming party Components of Teaming Agreement qualifications, insurance, matrix of responsibilities, confidentiality and exclusivity, payment of stipend/honoarrium URS CORP v TRANSPO - does teaming agreement waiver survive if subcontract supersedes teaming agreement? yes. subcontract was silent, waiver in prime flowed down. Common Procurement Challenges - conducting proprietary meetings - handling alternative technical concepts - evaluating non-price factors - consideration of all proposal information - use of work product fo unsuccessful proposers Standard form contracts - reflect industry consensus on risk allocation - predictable judicial interpretation - convenient and cost effective Current US Standard Form Contracts - DBIA (2010/2016) - Consensus Docs (2016) - AIA (2014) - EJDC (2016) DBIA OWNER/DESIGN-BUILDER AGREEMENTS - 520 Preliminary Agreement - 525 Lump Sum - 530 Cost Plus Fee with Option for GMP - 535 General Conditions - 545 Progressive Design-Build Contract for the Water/Wastewater Sector Contracting Approaches - Lump Sum - Cost Plus - GMP - Unit Prices - Target Pricing LUMP SUM (DBIA 525) - single price regardless of actual cost - no meaningful opportunity for Owner to be involved in subcontractor procurement - no transparency into lump sum price - limited audit rights - undisclosed contingencies COST PLUS/GMP (DBIA 530) - compensation based on actual cost plus fee up to GMP - owner had broad audit rights - owner has ability to be more involved ins subcontractor procurement - most contingencies are transparent - savings needs to be addressed - administratively more complex GMP PROCESS ISSUES - Timing of the GMP - Assumptions (schedule) - Contingency - Savings - Line item guarantees; not contemplated, general conditions could be capped Progressive Design-Build (PDB) - Design-builder retained by Owner early in projects's life primarily, if not exclusively, on qualifications - Final project cost and schedule commitment is not established as part of the selection process - Two phases of work: preliminary services, & final design and construction, once the parties have agreed on price and other commercial terms - GMP contract is often used PDB Process - Design-builder collaborates with Owner during Phase 1 to create or confirm project's BOD - Formal commercial proposal for Phase 2: "appropriate" level of definition often at 40-60% design; dependent on amount of control Owner desires to maintain over design definition and contingency - Phase 2 initiated upon acceptance of commercial proposal PDB Two-contract approach - parties first enter into a preliminary agreement, such as DBIA 520 (Preliminary Agreement) - if commercial proposal is accepted, parties then enter into a full design-build contract such as DBIA 530 (Cost-plus with GMP) PDB Single contract approach - parties enter into a full design-build contract (DBIA 530) or for water/wastewater, DBIA 545 - these contracts establish the GMP after contract award Progressive Design-Build Issue Deciding what happens if relationship ends and the "off-ramp" is exercised: - owner's right to use work product - owner's ability to use the designer without the builder OWNER'S REVIEW OF DESIGN SUBMISSIONS (DBIA 535) §2.4.1 On or about the time of the scheduled submissions, Design- Builder and Owner shall meet and confer about the submissions, withDesign- Builder identifying during the meeting, among other things, the evolution of the design and any significant changes or deviations that have taken place from previous design submissions. §2.4.3 Neither Owner's review nor approval of any interim design submissions, meeting minutes, and Construction Documents shall be deemed to transfer any design liability from Design-Builder to Owner. ADVANCETEC V WOHLSEN (2017) "Though Plaintiff may have made clear that it 'intended that Wohlsen's rights to use the [IOS] would terminate if AdvanceTEC was not selected as the subcontractor' and that it desired to retain the rights to the IOS until construction was complete, the Court finds that there is nothing in the Executed LOI to demonstrate that those intentions were ever perfected in the resulting document." DBIA Ownership of Work Product ▪ Work Product is property of design-builder ▪ Owner given limited license to use documents conditioned on ▪ Payment of monies due under agreement ▪ Indemnity to design-build team ▪ No indemnity if design-builder in default ▪ Agreed-upon premium to design-builder if: ▪ Preliminary agreement does not result in contract ▪ Owner terminates for convenience ▪ Parties can agree that Owner will have greater property rights ▪ Unique architectural and other design elements and specifications ▪ Full ownership of everything

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

3/30/25, 9:23 DBIA Flashcards |
AM
DBIA EXAM ACTUAL QUESTIONS AND ANSWERS WITH COMPLETE
SOLUTIONS VERIFIED GRADED A++

Terms in this set (175)


DBIA Document 580 - Teaming Between Design-Builder and teaming party
Agreement

qualifications, insurance, matrix of responsibilities, confidentiality and exclusivity,
Components of Teaming Agreement
payment of stipend/honoarrium

URS CORP v TRANSPO - does yes. subcontract was silent, waiver in prime flowed down.
teaming agreement waiver survive if
subcontract supersedes teaming
agreement?
- conducting proprietary meetings
- handling alternative technical concepts
Common Procurement Challenges - evaluating non-price factors
- consideration of all proposal information
- use of work product fo unsuccessful proposers

- reflect industry consensus on risk allocation
Standard form contracts - predictable judicial interpretation
- convenient and cost effective

- DBIA (2010/2016)
- Consensus Docs (2016)
Current US Standard Form Contracts
- AIA (2014)
- EJDC (2016)

- 520 Preliminary Agreement
- 525 Lump Sum
DBIA OWNER/DESIGN-BUILDER
- 530 Cost Plus Fee with Option for GMP
AGREEMENTS
- 535 General Conditions
- 545 Progressive Design-Build Contract for the Water/Wastewater Sector

- Lump Sum
- Cost Plus
Contracting Approaches - GMP
- Unit Prices
- Target Pricing

- single price regardless of actual cost
- no meaningful opportunity for Owner to be involved in subcontractor
procurement
LUMP SUM (DBIA 525)
- no transparency into lump sum price
- limited audit rights
- undisclosed contingencies

- compensation based on actual cost plus fee up to GMP
- owner had broad audit rights
- owner has ability to be more involved ins subcontractor procurement
COST PLUS/GMP (DBIA 530)
- most contingencies are transparent
- savings needs to be addressed
- administratively more complex

- Timing of the GMP
- Assumptions (schedule)
GMP PROCESS ISSUES - Contingency
- Savings
- Line item guarantees; not contemplated, general conditions could be capped




1/
9

, 3/30/25, 9:23 DBIA Flashcards |
AM
- Design-builder retained by Owner early in projects's life primarily, if
not exclusively, on qualifications
- Final project cost and schedule commitment is not established as part of
Progressive Design-Build (PDB) the selection process
- Two phases of work: preliminary services, & final design and construction,
once the parties have agreed on price and other commercial terms
- GMP contract is often used

- Design-builder collaborates with Owner during Phase 1 to create or confirm
project's BOD
- Formal commercial proposal for Phase 2: "appropriate" level of definition
PDB Process
often at 40-60% design; dependent on amount of control Owner desires to
maintain over design definition and contingency
- Phase 2 initiated upon acceptance of commercial proposal

- parties first enter into a preliminary agreement, such as DBIA 520 (Preliminary
Agreement)
PDB Two-contract approach
- if commercial proposal is accepted, parties then enter into a full design-build
contract such as DBIA 530 (Cost-plus with GMP)

- parties enter into a full design-build contract (DBIA 530) or for
PDB Single contract approach water/wastewater, DBIA 545
- these contracts establish the GMP after contract award

Deciding what happens if relationship ends and the "off-ramp" is exercised:
Progressive Design-Build Issue - owner's right to use work product
- owner's ability to use the designer without the builder

§2.4.1 On or about the time of the scheduled submissions, Design-
Builder and Owner shall meet and confer about the submissions, withDesign-
Builder identifying during the meeting, among other things, the evolution of the
OWNER'S REVIEW OF DESIGN
design and any significant changes or deviations that have taken place from
SUBMISSIONS
previous design submissions.
(DBIA 535)
§2.4.3 Neither Owner's review nor approval of any interim design
submissions, meeting minutes, and Construction Documents shall be
deemed to transfer any design liability from Design-Builder to Owner.

"Though Plaintiff may have made clear that it 'intended that Wohlsen's rights to
use the [IOS] would terminate if AdvanceTEC was not selected as the
subcontractor' and that it desired to retain the rights to the IOS until construction
ADVANCETEC V WOHLSEN (2017)
was complete, the Court finds that there is nothing in the Executed LOI to
demonstrate that those intentions were ever
perfected in the resulting document."


▪ Work Product is property of design-builder
▪ Owner given limited license to use documents conditioned on
▪ Payment of monies due under agreement
▪ Indemnity to design-build team
▪ No indemnity if design-builder in default
DBIA Ownership of Work Product ▪ Agreed-upon premium to design-builder if:
▪ Preliminary agreement does not result in contract
▪ Owner terminates for convenience
▪ Parties can agree that Owner will have greater property rights
▪ Unique architectural and other design elements and specifications
▪ Full ownership of everything




2/
9

Geschreven voor

Vak

Documentinformatie

Geüpload op
31 maart 2025
Aantal pagina's
9
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$11.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
AcademicSuperScores Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
299
Lid sinds
3 jaar
Aantal volgers
37
Documenten
7648
Laatst verkocht
1 week geleden
AcademicSuperScores

NURSING, ECONOMICS, MATHEMATICS, BIOLOGY AND HISTORY MATERIALS. BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS AND STUDY GUIDE MATERIALS WITH GUARANTEE OF A+ I am a dedicated medical practitioner with diverse knowledge in matters Nursing and Mathematics. I also have an additional knowledge in Mathematics based courses (finance and economics)

4.6

156 beoordelingen

5
125
4
9
3
11
2
5
1
6

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen