DBIA EXAM QUESTIONS AND ANSWERS WITH COMPLETE
SOLUTIONS VERIFIED GRADED A++ LATEST UPDATE
Terms in this set (127)
Idwp Integrated design work plan
PDRI Project definition rating index
BIM Building Information Modeling
What is the biggest item contributing to Absence of trust
team failure?
Manages design information flow and deliverables. Unique role that didn't exist
Design manager
before
Designer of record Manages design performance interface
Four primary phases of oversight Preconstruction, contract oversight, close-out, and performance evaluation
Formal partnering typically results A charter, communication matrix, and an issue resolution ladder
in mutually developing which
items?
What are the critical interfaces between Design&construct for value, design & construct to budget, design for
designer of record and contractor? constructibility, and design& construct for quality performance
Three requirements of estimating Functional, performance, and prescriptive
Offer Party offers to contract with another
Acceptance A party accepts the other party's offer
Consideration Value exchanged for performance
Capacity The party making the contract must be legally able to do so
Authority The individual forming the contract must have authority to do so
Betterment Doctrine Avoids windfalls- owner must pay first cost
Constructive change Change by implication-can be oral or written or omission
Insurance portion, for 3rd party claims, generally protects against liability, loss, or
Indemnity
damage
Liquidated Damages cost of late completion- cannot be a penalty
if contractor builds in compliance whether or not it works then contractor is not
Spearin Doctrine
held responsible
tort Law legally created; remedy to who was harmed
Contract Law Law between two parties
offer a party offers to contract with another (response to RFP)
acceptance a party accepts the other party's offer
capacity the party making the contract must be legally able to do so
consideration value exchanged for performance (money, services, etc.)
Authority the individual forming the contract must have authority to do so
unknown & hidden, concealed, or latent physical condition (ex. geotechnical
Differing Site Conditions Type 1
report incorrect)
encounters unknown physical conditions of unusual nature that differ materially
Differing Site Conditions Type 2 from those ordinarily encountered & generally recognized as inherent int he
work at the Project's location
Define GMP Guaranteed Maximum price