Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

DBIA TEST EXAM QUESTIONS AND ANSWERS WITH COMPLETE SOLUTIONS VERIFIED GRADED A++

Beoordeling
-
Verkocht
-
Pagina's
6
Cijfer
A+
Geüpload op
31-03-2025
Geschreven in
2024/2025

DBIA TEST EXAM QUESTIONS AND ANSWERS WITH COMPLETE SOLUTIONS VERIFIED GRADED A++ Terms in this set (109) Project Delivery System How team members are organized, establishes when parties engage, determines roles of parties, and determines sequence of design, procurement, and construction (db, cmar, dbb) Procurement Method how team members are selected (QBS, best value, low price, sole source) contracting approach how team members are paid (fp, gmp, cost reimbursement, target price, unit price) Design-Bid-Build (DBB) linear, sequential process, A/E selected on qualifications, GC selected on low price, design is fully completed without input from GC, A/E acting in owner's interests, with a historically strong bond, process is well-established and understood construction manager at risk similar org structure to DBB, construction manager selected by QBS or best value, contractor provides precon services, negotiated gmp contracting approach, open book estimating process, potential to fast track project, construction cost determined before design completed, potential issues over what is reasonably inferable from gmp design documents Design-Build The owner contracts with one entity (a person or firm) to provide both design and construction services, designer and contractor have a direct contractual relationship, selected by QBS or best value, wide spectrum of contracting approaches and organizational structures, single point responsibility, owner does not manage designer, owner exposure to claims is significantly reduced engineer procure construct (epc) similar to design build, in industrial and power generation sectors, systems and performance testing are central to scope, contractor will typically perform engineering with its in-house staff, owner has need for single point responsibility, contracts include plant and process performance guarantees, contract items include performance and schedule liquidated damages and limitations of liability Multiple Prime Contracting owner contracts with multiple trade contractors, attributes are typically similar to dbb, owner's ability to schedule and coordinate the work Integrated Project Delivery (IPD) multi-party agreement - all parties equal, QBS procurement and target pricing contract approach, private sector use (limited at this time), key: owner's ability to accept risk public-private partnership (p3) Instead of government building and maintaining major infrastructure (such as highway, water treatment plant), build and maintenance is outsourced to a private company. Opposed by public sector unions. this is not considered a delivery system but its underlying approaches are delivery systems and typically use DB. multiple procurement and contracting approaches shift left intense efforts to establish scope early in the process; drives early team formation to include key trade subcontractors; can enable big decisions to be made early, affect project outcomes at lowest cost, establish a need for co-location and collaboration, and compress time during concurrent design and construction traditional design build typically two-phase best value procurement with lump sum contract; owner defines project requirements and scope of prescriptive work; use of performance-based technical requirements with limited prescriptive specifications progressive design build design and price are progressively developed after the design-builder is under contract; final project cost and schedule commitment is not established as part of the selection process; two phases: preliminary services and final design and construction services criteria documents describe the end result bridging documents prescribes how to achieve the end result design bid build paradigm prior to bidding, owner undertakes a process to design the project and all of its details to 100% complete plans and specs. the owner is therefore responsible for success or failure of details of the design, and warrants the sufficiency of design to the contractor. the owner is therefore liable to the contractor for any gaps between plans and specifications and owner's requirements for project performance

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

3/30/25, 9:26
AM
DBIA TEST EXAM QUESTIONS AND ANSWERS WITH COMPLETE
SOLUTIONS VERIFIED GRADED A++
Terms in this set (109)


How team members are organized, establishes when parties engage, determines
Project Delivery System roles of parties, and determines sequence of design, procurement, and
construction (db, cmar, dbb)

Procurement Method how team members are selected (QBS, best value, low price, sole source)

how team members are paid (fp, gmp, cost reimbursement, target price, unit
contracting approach
price)

linear, sequential process, A/E selected on qualifications, GC selected on low
price, design is fully completed without input from GC, A/E acting in owner's
Design-Bid-Build (DBB)
interests, with a historically strong bond, process is well-established and
understood

similar org structure to DBB, construction manager selected by QBS or best value,
contractor provides precon services, negotiated gmp contracting approach,
construction manager at risk open book estimating process, potential to fast track project, construction cost
determined before design completed, potential issues over what is reasonably
inferable from gmp design documents

The owner contracts with one entity (a person or firm) to provide both design and
construction services, designer and contractor have a direct contractual
Design-Build relationship, selected by QBS or best value, wide spectrum of contracting
approaches and organizational structures, single point responsibility, owner does
not manage designer, owner exposure to claims is significantly reduced

similar to design build, in industrial and power generation sectors, systems and
performance testing are central to scope, contractor will typically perform
engineer procure construct (epc) engineering with its in-house staff, owner has need for single point
responsibility, contracts include plant and process performance guarantees,
contract items
include performance and schedule liquidated damages and limitations of liability
owner contracts with multiple trade contractors, attributes are typically similar to
Multiple Prime Contracting
dbb, owner's ability to schedule and coordinate the work

multi-party agreement - all parties equal, QBS procurement and target pricing
Integrated Project Delivery (IPD) contract approach, private sector use (limited at this time), key: owner's ability to
accept risk

Instead of government building and maintaining major infrastructure (such as
highway, water treatment plant), build and maintenance is outsourced to a private
public-private partnership (p3) company. Opposed by public sector unions. this is not considered a
delivery system but its underlying approaches are delivery systems and
typically use DB. multiple procurement and contracting approaches

intense efforts to establish scope early in the process; drives early team formation
to include key trade subcontractors; can enable big decisions to be made
shift left
early, affect project outcomes at lowest cost, establish a need for co-location
and
collaboration, and compress time during concurrent design and construction
typically two-phase best value procurement with lump sum contract; owner
defines project requirements and scope of prescriptive work; use of
traditional design build
performance-based technical requirements with limited prescriptive
specifications

design and price are progressively developed after the design-builder is under
contract; final project cost and schedule commitment is not established as part of
progressive design build
the selection process; two phases: preliminary services and final design and
construction services



1/
6

, 3/30/25, 9:26
AM


criteria documents describe the end result

bridging documents prescribes how to achieve the end result

prior to bidding, owner undertakes a process to design the project and all of its
details to 100% complete plans and specs. the owner is therefore responsible for
success or failure of details of the design, and warrants the sufficiency of design
design bid build paradigm
to the contractor. the owner is therefore liable to the contractor for any gaps
between plans and specifications and owner's requirements for project
performance

the owner should define its performance requirements and award the contract on
the basis of preliminary design; this makes the design-builder responsible for
completing the design in accordance with the owner's performance requirements.
design details responsibility
that also causes the design-builder to warrant the sufficiency of the design to
meet the owner's criteria and the sufficiency of the design to
subcontractors/suppliers that have no design responsibility

subdivides project by functional elements, focuses on systems and assemblies,
uniformat useful for preliminary information and early design phases, aligns with BIM models
and conceptual estimating

subdivides work by results/trades, focuses on building materials, products, and
masterformat activities, useful for detailed information during final design and construction
phases, and aligns with detailed estimating

a specific business need or behavior as seen by an external user of the system;
describe what functions/operations the end product must
functional requirement perform/accommodate; examples: regulatory, permitting, economic, and others
that define functions and operational capability. "Build an office building on my
existing lot to provide office space for 1,000 workers"

describes what product(s) components must do/achieve with a measurement
metric; challenges: developing objective and definable standards to validate
performance requirement performance, tendency to drift to prescriptive specs; examples: uniformat C10,
interior construction. "Provide durable, paintable interior walls between the
offices with STC 35 (min)"

describes in terms of exactly how the product and/or its components must be
built; cookbook approach; developed by the design builder but used by owners
in the RFP/bridging documents for operability or maintenance needs and
prescriptive requirement
conditions of permits or third parties; examples: uniformat C10, partitions. "Install
gypsum wallboard on 3-5/8" metal studs at 16" on center with XX acoustical
insulation per YY standards."


takes the best of "qualified" teams; a key to design-build success; not the same as
shortlisting prequalifying or pass/fail; keeping this small increases interest among the best
teams and minimizes procurement costs for everyone including the owner

owners define their goals and selection criteria, one or 2 phase process if
competitive procurement process shortlisting is applicable, price is not a factor in selection, award to most
qualified proposer, negotiate to a fair and reasonable price

qualifications, experience and past performance of design build team,
qualifications of key personnel, capacity of design build team to perform work,
QBS typical criteria team experience in working together, deisgn-builder's project management plan,
project-specific ideas demonstrating team's ability to innovate and think outside
of the box

selection criteria are price and non-price factors; 2 phase process: RFQ to
shortlist most highly qualified, RFP to obtain technical approach and price;
best value
determine evaluation factors and relative weighting; price proposals opened after
evaluation and scoring of technical proposals

technical score determined from multiple criteria and weighted scoring


2/
6

Geschreven voor

Vak

Documentinformatie

Geüpload op
31 maart 2025
Aantal pagina's
6
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$11.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
AcademicSuperScores Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
299
Lid sinds
3 jaar
Aantal volgers
37
Documenten
7648
Laatst verkocht
1 week geleden
AcademicSuperScores

NURSING, ECONOMICS, MATHEMATICS, BIOLOGY AND HISTORY MATERIALS. BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS AND STUDY GUIDE MATERIALS WITH GUARANTEE OF A+ I am a dedicated medical practitioner with diverse knowledge in matters Nursing and Mathematics. I also have an additional knowledge in Mathematics based courses (finance and economics)

4.6

156 beoordelingen

5
125
4
9
3
11
2
5
1
6

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen