CMGT 360 FINAL EXAM QUESTIONS AND ANSWERS WITH COMPLETE SOLUTIONS VERIFIED LATEST UPDATE 2025/2026 what are the steps of a project cycle in order? -recognizing a need -feasibility analysis performed to see if it makes sense to proceed with project -develop financing -project design & preconstruction -procure project where designer and owner have scope of project, cost, time done -construction now started by contractor -turnover and start up -operation of the facility -disposal of the project Who are the three major teams involved in construction? -project owner -designer (architect) -builder (contractor) primary tasks of an owner -select project team -select project delivery method -select type of contract -managing and funding the project primary tasks of a designer -creates design for project to meet owner needs -creates construction docs used to build project primary tasks of a contractor -contracts directly with owner -manages & coordinates all construction activities design bid build - 3 team members: owner, designer, builder - owner has contract with designer & builder construction manager at risk (CMAR) - 3 team members: owner, designer, CM/GC -can be fast tracked design build - 2 team members: owner and design-build entity -one contract -often fast tracked integrated project delivery (IPD) -team based approach to a project -often fast tracked public private partnerships - commonly used to build infrastructure ex: highways bridges, schools, hospitals what project delivery systems is riskiest to owner design bid build which type of contract does the contractor take on the most risk of cost overruns? lump sum which type of contract does the owner take on the most risk of cost overruns? cost plus fee Which of the following team members is hired by a designer? subconsultant

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

3/30/25, 9:33
AM
CMGT 360 FINAL EXAM QUESTIONS AND ANSWERS WITH COMPLETE
SOLUTIONS VERIFIED LATEST UPDATE 2025/2026

-recognizing a need
-feasibility analysis performed to see if it makes sense to proceed with project
-develop financing
-project design & preconstruction
what are the steps of a project cycle in -procure project where designer and owner have scope of project, cost, time
order? done
-construction now started by contractor
-turnover and start up
-operation of the facility
-disposal of the project

-project owner
Who are the three major teams
-designer (architect)
involved in construction?
-builder (contractor)

-select project team
-select project delivery method
primary tasks of an owner
-select type of contract
-managing and funding the project

-creates design for project to meet owner needs
primary tasks of a designer
-creates construction docs used to build project

-contracts directly with owner
primary tasks of a contractor
-manages & coordinates all construction activities

- 3 team members: owner, designer, builder
design bid build
- owner has contract with designer & builder

- 3 team members: owner, designer, CM/GC
construction manager at risk (CMAR)
-can be fast tracked

- 2 team members: owner and design-build entity
design build -one contract
-often fast tracked

-team based approach to a project
integrated project delivery (IPD)
-often fast tracked




1/
5

, 3/30/25, 9:33
AM
- commonly used to build infrastructure
public private partnerships
ex: highways bridges, schools, hospitals

what project delivery systems is riskiest to design bid build
owner

which type of contract does the lump sum
contractor take on the most risk of cost
overruns?

which type of contract does the owner cost plus fee
take on the most risk of cost overruns?

Which of the following team members is subconsultant
hired by a designer?

What is occurring during the schematic Designer investigates differing design alternatives for each system
design/schematic investigation phase of
design?

project delivery system riskiest to design build
contractor

-contractor provides a single price to perform the work based on plans and specs
lump sump contract -best used when scope is clear
-commonly used with design bid build

-contractor provides price for units of work
unit price contracts -best used when total work quantity is unknown
-commonly used on heavy civil projects for soil or rock work

-owner pays for the cost of the work
cost plus fee -best used when scope is not clearly defined
-commonly used for residential, emergency projects, fast paced projects

-maximum price ceiling is agreed upon which must not be exceeded
-if exceeded contracted party is responsible
cost plus fee with GMP
-commonly used for design and design build
-if final cost below gmp savings go to owner

A meeting agenda outlines the objectives true
of a meeting and is created before a
meeting

Meeting minutes are the record outcomes true
of a meeting and created during meeting

It is a best practice to create a project true
document control system before work
begins

An organizational system which allows a project manager to identify, track, and
Document Control
deliver all required documents in time to keep construction processes on time.

A Notice to Proceed cannot be sent false
until a final contract has been signed
by both parties.

A process in which one party sends documents to another party for their approval
Submittal for use in a project
-typically sub or gc asking for approval of designer/owner

A Storm Water Pollution Prevention Plan Which Best Management Practices will be used on site
should include:

site logistics plan Where temporary installations will be placed on site

Purchase orders -Document sent from buyers to sellers with a request to order products

What is the goal of value engineering? Increase design functionality and reduce life cycle costs




2/
5

Geschreven voor

Vak

Documentinformatie

Geüpload op
31 maart 2025
Aantal pagina's
5
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$10.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
AcademicSuperScores Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
299
Lid sinds
3 jaar
Aantal volgers
37
Documenten
7648
Laatst verkocht
1 week geleden
AcademicSuperScores

NURSING, ECONOMICS, MATHEMATICS, BIOLOGY AND HISTORY MATERIALS. BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS AND STUDY GUIDE MATERIALS WITH GUARANTEE OF A+ I am a dedicated medical practitioner with diverse knowledge in matters Nursing and Mathematics. I also have an additional knowledge in Mathematics based courses (finance and economics)

4.6

156 beoordelingen

5
125
4
9
3
11
2
5
1
6

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen