CMGT 360 FINAL (OTHER STUDENT) EXAM QUESTIONS AND ANSWERS
WITH COMPLETE SOLUTIONS VERIFIED
Terms in this set (57)
Contractor
led A/E led
5 DB Entity configurations Integrated Firm
Developer
Led Joint
Venture
Project delivery
What is Design-Build
Single contract with owner
RFP
DB Contract
Tech
3 initial DB contract Docs
Proposal Price
Proposal
• AIA (American Institute of Architects)
• EJCDC (Engineers Joint Contract Document Committee)
DB Standard Contracts
• AGC (Associated General Contractors Of America)
• DBIA (Design-Build Institute of America)
What determines who controls the details Level of design in the RFP
of design?
35% Design
Design Draw-Build Low bid-based
DB entity selected on price only to complete drawings
Defined as a written statement of requirements of
Programming the building used as the basis for design and the
Owner's budget & Schedule
An investigation of different design alternatives
Schematic Design
that meets the programming statement
Continuation of the Schematic design stage with
design schemes further developed on a system
Design Development -by
-
system basis with more detail
Architect creates final working construction
Construction Documents documents necessary to bid the job for construction,
pull permits and build the job in the field
Who Controls details of design in DBB The owner
Who controls details of Design in DB The Design-Builder
Owner warrants the sufficiency of the
Plans/Specs Warranty in DBB plans & specs to the Contractor
(Spearin)
The Design-Builder warrants the
Plans/Specs Warranty in DB sufficiency of the plans & specs to the
Owner
Single most important distinction of Team
Design Build
Gap Management Finding the holes and filling them
Bridging Owner Providing some level of design
1/