Terms in this set (108)
a method of project delivery in
which one entity (design-builder) forges a
Design-Build single contract with the Owner to provide for
architectural engineering design services
and construction services
• Contractor Led
• A/E Led
Design-Build Entity Configurations • Integrated Firm
• Developer Led
• Joint Venture
Competitive Solicitation IFB => Low Bid (quantitive only)
& Basis of Award
(Design-Bid-Build) (Slide 8)
Competitive Solicitation RFP => Best Value of ( Quantitative + Qualitative )
& Basis of Award
(Design-Build) (Slide 9)
• What constitutes the contract
differs significantly
Point of Contract • Impacts Roles of the Parties
• Impacts who owns the "details"
of the Design
Non-price items
• Package the Design-Build
• Technical Proposal team prepares for proposal:
includes drawings, written
specifications,
renderings, models and safety plans
Stipulated Sum proposed based on
Price Proposal
Technical Proposal
• AIA (American Institute of Architects)
Standard Form Design-Build • EJCDC (Engineers Joint Contract Document Committee)
Contracts • AGC (Associated General Contractors Of America)
• DBIA (Design-Build Institute of America)
Slide: 15
Contracts
Pricing is not addressed in AIA agreements
most significant distinction
Determines who controls the details of
• Level of design in RFP
the design
• If DB entity controls details of design
Design management
• Price only if DB does not control design
35% Design or Greater
Design Draw
• Typically Low Bid-Based
-Build
Procurement (price only/no technical)
1/10
, 3/30/25, 9:35 CMGT 360 Final (Exam 3) |
AM
Defined as a written statement of requirements of
the building used as the basis for design and the
Design Factors (Programming)
Owner's budget & Schedule
(10- 35%)
An investigation of different design alternatives
Design Factors (Schematic Design) that meets the programming statement
(10- 35%)
Continuation of the Schematic design stage with
Design Factors (Design Development) design schemes further developed on a system
by system basis with more detail
Architect creates final working construction
Design Factors (Construction Documents) documents necessary to bid the job for construction,
pull permits and build the job in the field
Who Controls the Details of the In Design-Bid-Build: the Owner does
Design? In Design-Build: The Design-Builder does
Design-Build like putting together a
puzzle
• The Owner's RFP is like putting
Owner "Approval" of Design
together the outside edges of the puzzle
• Perimeter will be the same...the
"HOW" will be apples and bananas
• Owner approves for "Compliance
Only" relative to RFP.
• Owner does not approve design
Owner "Approval" of Design
details and methods outside the
Owner's RFP performance &
programming
requirements
Design is Fixed - Design dictates
Design/Cost Relationship cost (and performance becomes a
Design-Bid-Build variable)
(Slide 23)
Designing to Budget
Design/Cost Relationship Design-Build Cost & Performance are Fixed
(Slide 24)
In Design-Bid-Build:
Plans/Specs Warranty • Owner warrants the sufficiency
of the plans & specs to the
(In Design-Bid-Build:) Contractor (Spearin)
• Owner owns the "details" of Design
The Design-Builder warrants the
Plans/Specs Warranty
sufficiency of the plans & specs to the
Owner
(Under Design-Build:)
• Design-Builder owns the "details" of Design
delivering
Design-Build allows for
beyond
expectations
Design-Build provides an opportunity to optimize all aspects of the solution
solutions that
Design-Build can deliver
otherwise could not have been envisioned