Terms in this set (60)
Project Life Cycle A project life cycle is the point from start to finish from planning to execution.
Project Management The administration portion of the project.
Project The awarded job to a company. One time job.
A successful project is characterized by... ...the satisfaction of stakeholders and owners of completed work.
Construction Management The encompassing of scope, quality, time and cost during the project's life cycle.
Facilitating functions of Producing Sequence
information/communication;
contracts/procurement; human
resources;risk.
Where we find what is to be managed. Planning Sequence
Where we find how we manage. Producing Sequence
Core management function of scope, Planning Sequence
quality, time and cost.
Planning sequence activities plus Project Management Integration Process
producing sequence activities equals
project success.
Discretionary permits issued by a review authority (Conditional Use
Entitlements
Permits, General Plan Amendments, Re-zoning, and Subdivision)
An entitlement that permits a non-permitted land use through approved
Conditional Use Permit conditions of approval even though the proposed land use does not conform to
the Zoning Plan Map and General Plan Map.
Zoning Plan Map Plan Map identifying land uses presently enforced by a Planning Department.
Comprehensive long-range vision of land use for a city or county required by
General Plan Map
state law.
Provides specific information as to the type of buildings allowed, building
Zoning Ordinances
setbacks, lot sizes, and allowed height for structures within a specific zoning.
Zoning regulations are an authority A
derived from the....to protect
public
health, safety and general welfare.
A) Police Power of Constitution
B) Planning Commission
C) City Council
D) General Plan
CEQA Protects....... D
A) Development interests
B) Builder interests
C) Quality of government
D) Quality of environment