Which of the following statements is NOT true? a. The government encourages the maximum practicable commercial use of inventions made under government contracts. b. The government recognizes rights in data developed at private expense, and limits its demands for delivery of that data. c. The government requires that contractors obtain permission from copyright owners before including copyrighted works, owned by others, in data to be delivered to the government. d. Generally, the government will refuse to award a contract on the grounds that the prospective contractor may infringe a patent. - d. Generally, the government will refuse to award a contract on the grounds that the prospective contractor may infringe a patent. FAR 27.102 Performance and payment bonds are required or may be required for a. construction contracts and services and supply contracts exceeding $2,000. b. construction contracts exceeding $150,000. c. any contract for services, d. construction contracts exceeding $150,000 and services and supply contracts exceeding the SAT when necessary to protect the governments interests. - d. construction contracts exceeding $150,000 and services and supply contracts exceeding the SAT when necessary to protect the governments interests. FAR 28.102-1(a), 28.103-1(a), 28.103-2(a) Cost Accounting Standards Board rules and regulations apply to

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

CFCM Study Guide: FULL TEST with Verified Answers
A+ Grade 100%.

Which of the following statements is NOT true?


a. The government encourages the maximum practicable commercial use of inventions made
under government contracts.
b. The government recognizes rights in data developed at private expense, and limits its demands
for delivery of that data.
c. The government requires that contractors obtain permission from copyright owners before
including copyrighted works, owned by others, in data to be delivered to the government.
d. Generally, the government will refuse to award a contract on the grounds that the prospective
contractor may infringe a patent. - d. Generally, the government will refuse to award a contract
on the grounds that the prospective contractor may infringe a patent.


FAR 27.102


Performance and payment bonds are required or may be required for


a. construction contracts and services and supply contracts exceeding $2,000.
b. construction contracts exceeding $150,000.
c. any contract for services,
d. construction contracts exceeding $150,000 and services and supply contracts exceeding the
SAT when necessary to protect the governments interests. - d. construction contracts exceeding
$150,000 and services and supply contracts exceeding the SAT when necessary to protect the
governments interests.


FAR 28.102-1(a), 28.103-1(a), 28.103-2(a)


Cost Accounting Standards Board rules and regulations apply to

,a. negotiated contracts and subcontracts.
b. sealed bid contracts.
c. contracts with small business concerns.
d. bridge contracts. - a. negotiated contracts and subcontracts.


FAR 30.000


The head of the agency may waive the applicability of Cost Accounting Standards (CAS) for a
particular contract or subcontract when one of these conditions exists:


a. The contract or subcontract is less than $50 million, primarily engaged in the sale of
commercial items, and has no contracts/subcontracts subject to CAS.
b. The contract or subcontract is less than $15 million, primarily engaged in the sale of
commercial items, and has no contracts/subcontracts subject to CAS.
c. The contract or subcontract is less than $7.5 million, primarily engaged in the sale of
commercial items.
d. The contract or subcontract is less than $5 million, primarily engaged in the sale of
commercial items, and has no contracts/subcontracts subject to CAS. - b. The contract or
subcontract is less than $15 million, primarily engaged in the sale of commercial items, and has
no contracts/subcontracts subject to CAS.


FAR 30.201-5


Which of the following statements about advance agreements is NOT true?


a. Advance agreements may only be negotiated with a particular contractor for a single contract.
b. Advance agreements may be negotiated either before or during a contract.
c. The agreement must be in writing.
d. The agreements must be incorporated into applicable current and future contracts. - a.
Advance agreements may only be negotiated with a particular contractor for a single contract.

,FAR 31.109


A cost is reasonable if, in its nature and amount, it does not exceed that which would be


a. incurred by a prudent person in the conduct of competitive business.
b. accrued by a prudent person in the conduct of competitive business.
c. determined to be allowable by the CO.
d. determined to be allocable by the CO. - a. incurred by a prudent person in the conduct of
competitive business.


FAR 31.201-3


What definition best describes alternative dispute resolution?


a. Procedures used to resolve issues in controversy.
b. Procedures voluntarily used to resolve issues in controversy.
c. Procedures used for asserting and resolving claims.
d. Procedures voluntarily used for asserting and resolving claims. - b. Procedures voluntarily
used to resolve issues in controversy.


FAR 33.214


The government's policy is to try to resolve all contractual issues in controversy by


a. mutual agreement at the CO's level.
b. bilateral agreement at the CO's level.
c. mutual agreement at a level above the CO.
d. unilateral agreement at the CO's level. - a. mutual agreement at the CO's level.


FAR 33.204

, After receiving the GAO's written notice that a protest has been filed, an agency must give notice


a. of the protest to the contractor or all parties who appear to have a reasonable prospect of
receiving an award.
b. of the protest only to the prime contractor performing the work.
c. of the protest to all parties who appear to have a reasonable prospect of receiving award and
begin compiling the information necessary to report to the GAO.
d. through a government-wide point of entry (GPE). - a. of the protest to the contractor or all
parties who appear to have a reasonable prospect of receiving an award.


FAR 33.104


Does a $75,000 claim resulting from a reduction of $350,000 and an increase of $275,000
require certification?


a. No, because the claimed amount is less than $100,000.
b. Yes, because the aggregate value of the claim exceeds $100,000.
c. No, because the claimed amount is less than $500,000.
d. Yes, because the aggregate value of the claim exceeds $500,000. - b. Yes, because the
aggregate value of the claim exceeds $100,000.


FAR 33.207(d)


Protests may be filed with


a. either the agency or the GAO.
b. the agency, the GAO, or the U.S. Court of Claims.
c. either the contracting officer or the U.S. Court of Federal Claims.
d. Small Claims Court for awards under the SAT. - b. the agency, the GAO, or the U.S. Court of
Claims.

Geschreven voor

Vak

Documentinformatie

Geüpload op
11 april 2025
Aantal pagina's
54
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$29.98
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
EXAMHUB1

Maak kennis met de verkoper

Seller avatar
EXAMHUB1 Cambridge University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
-
Lid sinds
2 jaar
Aantal volgers
0
Documenten
111
Laatst verkocht
-
EXAMHUB1

Hello! My name is EXAMHUB, and I’m an experienced and dedicated online tutor committed to helping students succeed. I provide study materials, notes, and guides to support your academic journey. Your feedback is highly valued, as it helps improve the quality of service and enhances your learning experience. Special Offer! For every student you refer who completes and pays for an order transparently, you’ll receive a free study document of your choice or a complimentary assignment completion! Thank you for your purchase! Please leave a review to share your experience and help others assess the quality of the documents. Your feedback is greatly appreciated!

Lees meer Lees minder
0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen