It is acceptable to measure the temperature of freshly mixed concrete in the forms
provide :
A. The sensor of the temperature measuring device has at least 3 " of cover in all
directions.
B. The concrete has been properly consolidated.
C. The sensor of the temperature measuring device is made of metal.
D. The concrete has been wet sieved. - (ANSWER)A. The sensor of the
temperature measuring device has at least 3 " of cover in all directions.
The temperature measuring devices shall be capable of accurately measuring the
temperature of freshly mixed concrete to 1 ° F throughout a range of
________________.
A. 20 - 100 ° F
,B. 45 - 95 ° F
C. 30 - 120 ° F
D. 50 - 200 ° F - (ANSWER)C. 30 - 120 ° F
Is the following statement true or false?
Composite samples are required even if the only purpose for obtaining the sample
is to determine temperature.
A. True
B. False - (ANSWER)B. False
The temperature measuring device is left in the freshly mixed concrete for at least
__________ but not more than 5 minutes.
A. 10 seconds
B. 30 seconds
, C. 1 minute
D. 2 minutes - (ANSWER)D. 2 mintues
Is the following statement true or false?
Test Method C1064/C1064 specifies a maximum temperature of freshly mixed
concrete.
A. True
B. False - (ANSWER)B. False
The elapsed time between obtaining the first and final portion of a composite
sample shall not exceed___________.
A. 15 minutes
B. 20 minutes
C. 30 minutes